9000 W 3RD ST 90048
APPLICATION / PERMIT NUMBER: 14041-10000-16757
PLAN CHECK / JOB NUMBER: E14LA02202

Plan Check and Permit Information


GROUP: Electrical
TYPE: Electrical
SUB-TYPE: Apartment
PRIMARY USE: N/A
WORK DESCRIPTION: New High-Rise Residential Building : Type 1-A , 13 story 58 apartments + 1 core & shell apartment on 12th &13th floor ( penthouse) over three level of subterranean parking. Ground floor Core and shell for 1) Gymnasium 2) Private Threatre 3) Lounge-Kitchen. And Basement level 1 Kitchen Core and shell.
PERMIT ISSUED: Yes PERMIT ISSUE DATE: 06/28/2017 ISSUING OFFICE: Metro
CURRENT STATUS: Permit Finaled CURRENT STATUS DATE: 02/14/2022

Permit Application Status History
Submitted 06/30/2014 APPLICANT
Assigned to Plan Check Engineer 08/14/2014 MEHDI ZANDI
Corrections Issued 08/17/2014 MEHDI ZANDI
Quality Review Completed 08/21/2014 NABIL MAALOUF
Applicant returned to address corrections 07/22/2015 MEHDI ZANDI
Applicant returned to address corrections 08/13/2015 MEHDI ZANDI
Applicant returned to address corrections 10/09/2015 MEHDI ZANDI
Plan Check Approved 10/28/2015 MEHDI ZANDI
Issued 06/28/2017 LADBS
Permit Finaled 02/14/2022 MATTHEW COTTER

Permit Application Clearance Information
  No data available

Licensed Professional/Contractor Information
Contractor Information
Sasco; Lic. No.: 125897-C10
2750 MOORE AVENUE
FULLERTON, CA  92833
Engineer Information
Brownlee, Amanda Jane; Lic. No.: E17287
405 HOWARD ST STE 500
SAN FRANCISCO, CA  94105

Inspection Activity Information

Inspector Information
DENNIS BROMMER, (213) 482-0305
Office Hours: 7:00-8:00 AM MON-FRI
STEVE SMAY, (213) 482-0305
Office Hours: 7:00-8:00 AM MON-FRI
MATTHEW COTTER, (213) 482-0305
Office Hours: 7:00-8:00 AM MON-FRI
JAKE MARTINEK, (213) 482-0305
Office Hours: 7:00-8:00 AM MON-FRI
ADAM POLDER, (213) 482-0305
Office Hours: 7:00-8:00 AM MON-FRI
DAVID KOSKI, (213) 482-0305
Office Hours: 7:00-8:00 AM MON-FRI
RODNEY LANE, (213) 482-0305
Office Hours: 7:00-8:00 AM MON-FRI
ROBERT STUCZYNSKI, (213) 482-0305
Office Hours: 7:00-8:00 AM MON-FRI
JOSE CONSUEGRA, (213) 482-0305
Office Hours: 7:00-8:00 AM MON-FRI
KEROP KETSOYAN, (213) 482-0305
Office Hours: 7:00-8:00 AM MON-FRI
JOHN ANAGNOSTOU, (213) 482-0305
Office Hours: 7:00-8:00 AM MON-FRI
ALEJANDRO ALVARADO, (213) 482-0305
Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspection Request(s)
  No data available

Inspection Request History
  Underground   12/14/2017   Partial Approval   ANTHONY GOVERNO
  Underground   12/27/2017   Partial Approval   ANTHONY GOVERNO
  Underground   01/02/2018   Partial Approval   RICHARD HORN
  Underground   01/03/2018   Partial Approval   ANTHONY GOVERNO
  Underground   01/05/2018   Partial Approval   ANTHONY GOVERNO
  Underground   01/08/2018   Partial Approval   ANTHONY GOVERNO
  Underground   01/12/2018   Partial Approval   ANTHONY GOVERNO
  Underground   01/19/2018   Partial Approval   ANTHONY GOVERNO
  Underground   01/24/2018   Partial Approval   ANTHONY GOVERNO
  Underground   01/25/2018   Partial Approval   RICHARD HORN
  Underground   01/30/2018   Partial Approval   RICHARD HORN
  Underground   02/01/2018   Partial Approval   RICHARD HORN
  Underground   02/07/2018   Partial Approval   ANTHONY GOVERNO
  Underground   02/08/2018   Partial Approval   ANTHONY GOVERNO
  Underground   02/13/2018   Partial Approval   ANTHONY GOVERNO
  Underground   02/15/2018   Partial Approval   ANTHONY GOVERNO
  Underground   02/16/2018   Partial Approval   ANTHONY GOVERNO
  Underground   02/21/2018   Partial Approval   ANTHONY GOVERNO
  Underground   02/26/2018   Partial Approval   WILLIAM MITCHELL
  Underground   02/27/2018   Partial Approval   WILLIAM MITCHELL
  Underground   03/01/2018   Partial Approval   ANTHONY GOVERNO
  Underground   03/05/2018   Partial Approval   ANTHONY GOVERNO
  Underground   03/06/2018   Partial Approval   JULIE HAZUKA
  Underground   03/07/2018   Partial Approval   ANTHONY GOVERNO
  Underground   03/12/2018   Partial Approval   MICHAEL KION
  Underground   03/14/2018   Partial Approval   MICHAEL KION
  Underground   03/15/2018   Partial Approval   MICHAEL KION
  Underground   03/16/2018   Partial Approval   ANTHONY GOVERNO
  Underground   03/20/2018   Partial Approval   MICHAEL KION
  Underground   03/23/2018   Partial Approval   MICHAEL KION
  Underground   03/27/2018   Partial Approval   MICHAEL KION
  Underground   04/06/2018   Corrections Issued   ANTHONY GOVERNO
  Underground   04/10/2018   Partial Approval   ANTHONY GOVERNO
  Underground   04/12/2018   Partial Approval   PHILIP FERGUSON
  Underground   04/19/2018   Partial Approval   MICHAEL KION
  Underground   04/23/2018   Partial Approval   MICHAEL KION
  Underground   04/25/2018   Partial Approval   MICHAEL KION
  Underground   04/30/2018   Partial Approval   ANTHONY GOVERNO
  Underground   05/01/2018   Partial Approval   ANTHONY GOVERNO
  Underground   05/02/2018   Partial Approval   MICHAEL KION
  Underground   05/08/2018   Partial Approval   ANTHONY GOVERNO
  Underground   05/10/2018   Partial Approval   ANTHONY GOVERNO
  Underground   05/15/2018   Partial Approval   ANTHONY GOVERNO
  Underground   05/17/2018   Partial Approval   ANTHONY GOVERNO
  Underground   05/22/2018   Partial Approval   ANTHONY GOVERNO
  Underground   05/25/2018   Partial Approval   MICHAEL KION
  Underground   05/30/2018   Partial Approval   MICHAEL KION
  Underground   05/31/2018   Partial Approval   MICHAEL KION
  Underground   06/05/2018   Partial Approval   MICHAEL KION
  Underground   06/07/2018   Partial Approval   ANTHONY GOVERNO
  Underground   06/13/2018   Partial Approval   ANTHONY GOVERNO
  Underground   06/18/2018   Partial Approval   ANTHONY GOVERNO
  Underground   06/26/2018   Partial Approval   ANTHONY GOVERNO
  Underground   06/27/2018   Partial Approval   ANTHONY GOVERNO
  Underground   07/05/2018   Partial Approval   MICHAEL KION
  Underground   07/06/2018   Partial Approval   MICHAEL KION
  Underground   07/09/2018   Partial Approval   ANTHONY GOVERNO
  Underground   07/11/2018   Partial Approval   ANTHONY GOVERNO
  Underground   07/13/2018   Partial Approval   ANTHONY GOVERNO
  Underground   07/19/2018   Partial Approval   ANTHONY GOVERNO
  Underground   07/24/2018   Not Ready for Inspection   ANTHONY GOVERNO
  Underground   07/25/2018   Partial Approval   ANTHONY GOVERNO
  Underground   08/02/2018   Partial Approval   ANTHONY GOVERNO
  Underground   08/13/2018   Partial Approval   ANTHONY GOVERNO
  Underground   08/20/2018   Partial Approval   ANTHONY GOVERNO
  Construction Power(CTS)   08/28/2018   Not Ready for Inspection   ANTHONY GOVERNO
  Underground   08/28/2018   Partial Approval   ANTHONY GOVERNO
  Underground   09/04/2018   Partial Approval   ANTHONY GOVERNO
  Underground   09/05/2018   Partial Approval   ANTHONY GOVERNO
  Underground   09/06/2018   Not Ready for Inspection   ANTHONY GOVERNO
  Underground   09/07/2018   Partial Approval   WILFRED LOMELI
  Underground   09/13/2018   Partial Approval   ANTHONY GOVERNO
  Underground   09/14/2018   No Access for Inspection   JULIE HAZUKA
  Underground   09/24/2018   Partial Approval   MICHAEL KION
  Underground   09/27/2018   Partial Approval   ANTHONY GOVERNO
  Underground   10/05/2018   Partial Approval   ANTHONY GOVERNO
  Underground   10/09/2018   Partial Approval   ANTHONY GOVERNO
  Rough   10/10/2018   Off-Hour Fees Due   
  Rough   10/15/2018   Partial Approval   ADAM POLDER
  Underground   10/15/2018   Partial Approval   ADAM POLDER
  Rough   10/19/2018   Conditional Approval   MICHAEL PACKARD
  Rough   10/29/2018   Partial Approval   MICHAEL PACKARD
  Rough   11/07/2018   Partial Approval   MICHAEL PACKARD
  Underground   11/15/2018   Not Ready for Inspection   DAVID HAENDLE
  Underground   11/16/2018   Partial Approval   DAVID HAENDLE
  Underground   12/10/2018   Partial Approval   ADAM POLDER
  Rough   12/12/2018   Partial Inspection   DAVID HAENDLE
  Rough   12/19/2018   Partial Approval   DAVID HAENDLE
  Underground   12/27/2018   Off-Hour Fees Due   
  Underground   12/27/2018   Partial Inspection   ANTHONY SIMPSON
  Rough   01/02/2019   Partial Approval   DAVID HAENDLE
  Service/Power Release   01/02/2019   Corrections Issued   DAVID HAENDLE
  Service/Power Release   01/11/2019   Partial Inspection   DAVID HAENDLE
  Rough   01/17/2019   Partial Approval   DAVID HAENDLE
  Service/Power Release   01/17/2019   Partial Inspection   DAVID HAENDLE
  Underground   01/17/2019   No Access for Inspection   DAVID HAENDLE
  Underground   01/18/2019   Partial Approval   DAVID HAENDLE
  Underground   02/22/2019   Partial Approval   DAVID HAENDLE
  Rough   02/27/2019   Partial Approval   DAVID HAENDLE
  Service/Power Release   03/07/2019   Corrections Issued   DAVID HAENDLE
  Rough   03/12/2019   Partial Approval   DAVID HAENDLE
  Underground   03/15/2019   Partial Approval   MICHAEL KION
  Service/Power Release   03/20/2019   Off-Hour Fees Due   
  Service/Power Release   03/20/2019   Partial Approval   STEVE SMAY
  Service/Power Release   03/29/2019   Partial Approval   DAVID HAENDLE
  Underground   04/08/2019   Partial Approval   DAVID HAENDLE
  Service/Power Release   04/23/2019   Partial Inspection   DAVID HAENDLE
  Rough   04/29/2019   Partial Inspection   DAVID HAENDLE
  Service/Power Release   04/29/2019   Partial Inspection   DAVID HAENDLE
  Rough   05/08/2019   Partial Inspection   DAVID HAENDLE
  Service/Power Release   05/08/2019   Partial Inspection   DAVID HAENDLE
  Service/Power Release   05/13/2019   Partial Inspection   DAVID HAENDLE
  Rough   06/04/2019   Partial Approval   JOHNNY YUTRONICH
  Service/Power Release   06/17/2019   Partial Inspection   DAVID HAENDLE
  Special Equipment   06/17/2019   Partial Approval   DAVID HAENDLE
  Service/Power Release   06/21/2019   Partial Inspection   DAVID HAENDLE
  Service/Power Release   06/28/2019   Partial Inspection   DAVID HAENDLE
  Service/Power Release   07/02/2019   Partial Inspection   DAVID HAENDLE
  Rough   07/03/2019   Corrections Issued   DAVID HAENDLE
  Rough   07/12/2019   Partial Approval   STEVE SMAY
  Rough   07/18/2019   Partial Approval   DAVID HAENDLE
  Service/Power Release   07/18/2019   Partial Inspection   DAVID HAENDLE
  Rough   07/23/2019   Corrections Issued   DAVID HAENDLE
  Service/Power Release   07/25/2019   Partial Inspection   DAVID HAENDLE
  Service/Power Release   07/26/2019   Partial Inspection   DAVID HAENDLE
  Service/Power Release   07/29/2019   Partial Inspection   DAVID HAENDLE
  Service/Power Release   07/30/2019   Partial Inspection   DAVID HAENDLE
  Rough   08/02/2019   Partial Approval   DAVID HAENDLE
  Service/Power Release   08/02/2019   Not Ready for Inspection   DAVID HAENDLE
  Rough   08/05/2019   Not Ready for Inspection   DAVID HAENDLE
  Rough   08/08/2019   Not Ready for Inspection   DAVID HAENDLE
  Service/Power Release   08/08/2019   Partial Inspection   DAVID HAENDLE
  Rough   08/09/2019   Corrections Issued   DAVID HAENDLE
  Rough   08/13/2019   Partial Inspection   DAVID HAENDLE
  Service/Power Release   08/14/2019   Partial Inspection   DAVID HAENDLE
  Rough   08/15/2019   Partial Approval   DAVID HAENDLE
  Service/Power Release   08/19/2019   Partial Inspection   DAVID HAENDLE
  Rough   08/20/2019   Partial Approval   DAVID HAENDLE
  Service/Power Release   08/20/2019   Approved   DAVID HAENDLE
  Rough   08/27/2019   Partial Inspection   DAVID HAENDLE
  Service/Power Release   08/27/2019   Partial Inspection   DAVID HAENDLE
  Rough   09/03/2019   Not Ready for Inspection   DAVID HAENDLE
  Service/Power Release   09/03/2019   Partial Inspection   DAVID HAENDLE
  Rough   09/04/2019   Partial Approval   JOHNNY YUTRONICH
  Rough   09/09/2019   Corrections Issued   JOHNNY YUTRONICH
  Rough   09/10/2019   Partial Approval   JOHNNY YUTRONICH
  Service/Power Release   09/10/2019   Partial Approval   JOHNNY YUTRONICH
  Rough   09/13/2019   Corrections Issued   DAVID HAENDLE
  Service/Power Release   09/13/2019   Partial Approval   DAVID HAENDLE
  Service/Power Release   09/16/2019   Corrections Issued   DAVID HAENDLE
  Rough   09/20/2019   Corrections Issued   DAVID HAENDLE
  Rough   09/25/2019   Partial Approval   DAVID HAENDLE
  Special Equipment   09/25/2019   Partial Approval   DAVID HAENDLE
  Rough   09/26/2019   Not Ready for Inspection   DAVID HAENDLE
  Service/Power Release   09/26/2019   Partial Inspection   DAVID HAENDLE
  Rough   09/30/2019   Partial Approval   DAVID HAENDLE
  Rough   10/02/2019   Partial Approval   STEVE SMAY
  Service/Power Release   10/02/2019   Partial Inspection   DAVID HAENDLE
  Special Equipment   10/04/2019   Corrections Issued   DAVID HAENDLE
  Rough   10/07/2019   Corrections Issued   DAVID HAENDLE
  Special Equipment   10/09/2019   Corrections Issued   DAVID HAENDLE
  Rough   10/11/2019   Partial Approval   STEVE SMAY
  Special Equipment   10/11/2019   Not Ready for Inspection   STEVE SMAY
  Rough   10/18/2019   Corrections Issued   DAVID HAENDLE
  Rough   10/21/2019   Partial Inspection   JOHNNY YUTRONICH
  Special Equipment   10/21/2019   Partial Inspection   JOHNNY YUTRONICH
  Special Equipment   10/23/2019   Partial Approval   RICHARD HORN
  Rough   10/25/2019   Partial Approval   DAVID HAENDLE
  Rough   10/28/2019   Partial Approval   DAVID HAENDLE
  Special Equipment   10/28/2019   Partial Approval   DAVID HAENDLE
  Service/Power Release   10/29/2019   Partial Inspection   DAVID HAENDLE
  Rough   10/31/2019   Partial Approval   DAVID HAENDLE
  Service/Power Release   10/31/2019   Partial Inspection   DAVID HAENDLE
  Rough   11/04/2019   Partial Approval   JOHN SPRINGER
  Special Equipment   11/04/2019   Partial Approval   JOHN SPRINGER
  Underground   11/06/2019   Partial Approval   DAVID HAENDLE
  Rough   11/08/2019   Partial Approval   DAVID HAENDLE
  Rough   11/13/2019   Partial Approval   DAVID HAENDLE
  Special Equipment   11/13/2019   Corrections Issued   DAVID HAENDLE
  Rough   11/15/2019   Corrections Issued   DAVID HAENDLE
  Special Equipment   11/15/2019   Partial Approval   DAVID HAENDLE
  Service/Power Release   11/20/2019   Partial Inspection   DAVID HAENDLE
  Rough   11/22/2019   Partial Approval   DAVID HAENDLE
  Service/Power Release   11/25/2019   Corrections Issued   DAVID HAENDLE
  Life Safety   11/27/2019   Partial Inspection   ANTHONY SIMPSON
  Rough   11/27/2019   Partial Inspection   ANTHONY SIMPSON
  Special Equipment   11/27/2019   Partial Inspection   ANTHONY SIMPSON
  Service/Power Release   12/02/2019   Partial Inspection   DAVID HAENDLE
  Service/Power Release   12/05/2019   Partial Inspection   DAVID HAENDLE
  Rough   12/07/2019   Off-Hour Fees Due   
  Rough   12/07/2019   Partial Approval   RICHARD HORN
  Special Equipment   12/07/2019   Off-Hour Fees Due   
  Special Equipment   12/07/2019   Partial Approval   RICHARD HORN
  Underground   12/07/2019   Partial Approval   RICHARD HORN
  Rough   12/10/2019   Partial Approval   MICHAEL KION
  Special Equipment   12/10/2019   Partial Approval   MICHAEL KION
  Rough   12/13/2019   Partial Approval   JIMMY MEJIA
  Rough   12/18/2019   Partial Approval   RICHARD HORN
  Rough   12/19/2019   Partial Approval   EDWARD ZAVALA
  Special Equipment   12/19/2019   Partial Approval   EDWARD ZAVALA
  Rough   12/20/2019   Partial Approval   EDWARD ZAVALA
  Special Equipment   12/20/2019   Partial Approval   EDWARD ZAVALA
  Rough   12/30/2019   No Access for Inspection   EDWARD ZAVALA
  Special Equipment   12/30/2019   No Access for Inspection   EDWARD ZAVALA
  Rough   12/31/2019   Partial Approval   EDWARD ZAVALA
  Special Equipment   12/31/2019   Partial Approval   EDWARD ZAVALA
  Rough   01/06/2020   Partial Approval   JOHNNY YUTRONICH
  Special Equipment   01/06/2020   Partial Approval   JOHNNY YUTRONICH
  Rough   01/07/2020   Partial Approval   EDWARD ZAVALA
  Special Equipment   01/07/2020   Partial Approval   EDWARD ZAVALA
  Special Equipment   01/09/2020   No Access for Inspection   EDWARD ZAVALA
  Service/Power Release   01/10/2020   Partial Approval   EDWARD ZAVALA
  Rough   01/14/2020   Partial Inspection   JOHNNY YUTRONICH
  Special Equipment   01/14/2020   Not Ready for Inspection   JOHNNY YUTRONICH
  Rough   01/17/2020   Partial Approval   JAKE MARTINEK
  Special Equipment   01/17/2020   Partial Approval   JAKE MARTINEK
  Rough   01/22/2020   Partial Inspection   DAVID HAENDLE
  Special Equipment   01/22/2020   Partial Inspection   DAVID HAENDLE
  Rough   01/23/2020   Corrections Issued   PANHNHAPUN YOU
  Special Equipment   01/23/2020   Partial Approval   PANHNHAPUN YOU
  Service/Power Release   01/27/2020   Partial Inspection   DAVID HAENDLE
  Special Equipment   01/27/2020   Partial Inspection   DAVID HAENDLE
  Service/Power Release   01/30/2020   Partial Inspection   DAVID HAENDLE
  Special Equipment   02/03/2020   Partial Approval   DAVID HAENDLE
  Service/Power Release   02/04/2020   Partial Inspection   DAVID HAENDLE
  Rough   02/05/2020   Corrections Issued   DAVID HAENDLE
  Rough   02/07/2020   Partial Approval   DAVID HAENDLE
  Special Equipment   02/12/2020   Not Ready for Inspection   DAVID HAENDLE
  Rough   02/19/2020   Partial Approval   MICHAEL KION
  Special Equipment   02/19/2020   Partial Approval   MICHAEL KION
  Service/Power Release   02/21/2020   Partial Inspection   DAVID HAENDLE
  Special Equipment   02/21/2020   Partial Inspection   DAVID HAENDLE
  Special Equipment   02/25/2020   Corrections Issued   DAVID HAENDLE
  Rough   02/27/2020   Corrections Issued   JAKE MARTINEK
  Special Equipment   02/27/2020   Not Ready for Inspection   JAKE MARTINEK
  Rough   03/03/2020   Partial Approval   DAVID HAENDLE
  Special Equipment   03/03/2020   Corrections Issued   DAVID HAENDLE
  Rough   03/05/2020   Partial Approval   JAKE MARTINEK
  Rough   03/09/2020   Corrections Issued   DAVID HAENDLE
  Rough   03/13/2020   Partial Approval   DAVID HAENDLE
  Special Equipment   03/13/2020   Partial Approval   DAVID HAENDLE
  Rough   03/17/2020   Partial Approval   DAVID HAENDLE
  Special Equipment   03/17/2020   Partial Inspection   DAVID HAENDLE
  Rough   03/18/2020   Partial Approval   DAVID HAENDLE
  Special Equipment   03/18/2020   Partial Approval   DAVID HAENDLE
  Rough   03/20/2020   Partial Approval   DAVID HAENDLE
  Special Equipment   03/20/2020   Partial Approval   DAVID HAENDLE
  Rough   03/24/2020   Partial Inspection   DAVID HAENDLE
  Special Equipment   03/24/2020   Partial Approval   DAVID HAENDLE
  Special Equipment   03/25/2020   Corrections Issued   DAVID HAENDLE
  Special Equipment   03/26/2020   Corrections Issued   DAVID HAENDLE
  Rough   03/31/2020   Partial Approval   DAVID HAENDLE
  Special Equipment   03/31/2020   Corrections Issued   DAVID HAENDLE
  Rough   04/17/2020   Partial Approval   DAVID HAENDLE
  Special Equipment   04/17/2020   Not Ready for Inspection   DAVID HAENDLE
  Rough   04/20/2020   Partial Approval   DAVID HAENDLE
  Special Equipment   04/20/2020   Corrections Issued   DAVID HAENDLE
  Rough   04/21/2020   Partial Inspection   DAVID HAENDLE
  Special Equipment   04/21/2020   Partial Approval   DAVID HAENDLE
  Rough   04/24/2020   Partial Approval   DAVID HAENDLE
  Special Equipment   04/24/2020   Partial Inspection   DAVID HAENDLE
  Final   04/30/2020   Corrections Issued   DAVID HAENDLE
  Service/Power Release   04/30/2020   Partial Inspection   DAVID HAENDLE
  Special Equipment   05/06/2020   Corrections Issued   DAVID HAENDLE
  Special Equipment   05/14/2020   Corrections Issued   DAVID HAENDLE
  Special Equipment   05/21/2020   Corrections Issued   DAVID HAENDLE
  Rough   05/22/2020   Partial Approval   DAVID HAENDLE
  Special Equipment   05/22/2020   Partial Approval   DAVID HAENDLE
  Rough   06/02/2020   Partial Approval   DAVID HAENDLE
  Service/Power Release   06/02/2020   Partial Inspection   DAVID HAENDLE
  Rough   06/04/2020   Partial Approval   DAVID HAENDLE
  Special Equipment   06/04/2020   Corrections Issued   DAVID HAENDLE
  Rough   06/24/2020   Partial Approval   ERIC BANE
  Special Equipment   06/24/2020   Partial Approval   ERIC BANE
  Special Equipment   06/30/2020   Corrections Issued   ERIC BANE
  Special Equipment   07/14/2020   Partial Approval   DAVID HAENDLE
  Rough   07/22/2020   Corrections Issued   DAVID HAENDLE
  Special Equipment   07/22/2020   Partial Inspection   DAVID HAENDLE
  Rough   08/05/2020   Partial Approval   ERIC BANE
  Special Equipment   08/05/2020   Partial Approval   ERIC BANE
  Rough   08/11/2020   Partial Approval   DAVID HAENDLE
  Special Equipment   08/11/2020   Partial Approval   DAVID HAENDLE
  Special Equipment   08/25/2020   Corrections Issued   DAVID HAENDLE
  Rough   09/01/2020   Partial Inspection   DAVID HAENDLE
  Service/Power Release   09/01/2020   Corrections Issued   DAVID HAENDLE
  Special Equipment   09/09/2020   Corrections Issued   DAVID HAENDLE
  Final   09/10/2020   Partial Approval   DAVID HAENDLE
  Rough   09/10/2020   Partial Approval   DAVID HAENDLE
  Special Equipment   09/11/2020   Partial Approval   DAVID HAENDLE
  Special/Order Compliance   09/11/2020   Corrections Issued   DAVID HAENDLE
  Final   09/17/2020   Partial Approval   DAVID HAENDLE
  Final   09/18/2020   Partial Inspection   DAVID HAENDLE
  Life Safety   09/18/2020   Partial Inspection   DAVID HAENDLE
  Final   09/19/2020   Off-Hour Fees Due   
  Life Safety   09/22/2020   Partial Approval   RICHARD HORN
  Special Equipment   09/22/2020   Partial Approval   RICHARD HORN
  Special Equipment   09/25/2020   Partial Approval   DAVID HAENDLE
  Final   09/26/2020   Corrections Issued   DAVID HAENDLE
  Special Equipment   09/28/2020   Corrections Issued   DAVID HAENDLE
  Special Equipment   09/30/2020   Not Ready for Inspection   DAVID HAENDLE
  Final   10/01/2020   Corrections Issued   DAVID HAENDLE
  Final   10/02/2020   Corrections Issued   DAVID HAENDLE
  Special Equipment   10/02/2020   Partial Inspection   DAVID HAENDLE
  Life Safety   10/03/2020   Partial Inspection   DAVID HAENDLE
  Service/Power Release   10/03/2020   Corrections Issued   DAVID HAENDLE
  Final   10/05/2020   Corrections Issued   DAVID HAENDLE
  Final   10/06/2020   Corrections Issued   DAVID HAENDLE
  Special Equipment   10/08/2020   Corrections Issued   DAVID HAENDLE
  Life Safety   10/09/2020   Partial Inspection   DAVID HAENDLE
  Life Safety   10/15/2020   Partial Approval   DAVID HAENDLE
  Life Safety   10/19/2020   Partial Approval   DAVID HAENDLE
  Life Safety   10/21/2020   Approved   DAVID HAENDLE
  Rough   10/21/2020   Partial Approval   DAVID HAENDLE
  Final   10/23/2020   Corrections Issued   DAVID HAENDLE
  Life Safety   10/23/2020   Approved   DAVID HAENDLE
  Final   10/24/2020   Corrections Issued   DAVID HAENDLE
  Final   10/26/2020   Corrections Issued   DAVID HAENDLE
  Life Safety   10/26/2020   Approved   DAVID HAENDLE
  Final   10/28/2020   Partial Inspection   DAVID HAENDLE
  Underground   10/28/2020   Partial Approval   DAVID HAENDLE
  Special Equipment   10/29/2020   Partial Inspection   DAVID HAENDLE
  Special Equipment   10/30/2020   Partial Approval   DAVID HAENDLE
  Special Equipment   10/31/2020   Partial Approval   DAVID HAENDLE
  Life Safety   11/04/2020   Approved   DAVID HAENDLE
  Special Equipment   11/04/2020   Partial Inspection   DAVID HAENDLE
  Life Safety   11/05/2020   Approved   DAVID HAENDLE
  Special Equipment   11/05/2020   Partial Approval   DAVID HAENDLE
  Rough   11/10/2020   Off-Hour Fees Due   
  Life Safety   11/24/2020   Not Ready for Inspection   DAVID HAENDLE
  Special Equipment   11/24/2020   Not Ready for Inspection   DAVID HAENDLE
  Life Safety   11/30/2020   Approved   DAVID HAENDLE
  Special Equipment   11/30/2020   Partial Approval   DAVID HAENDLE
  Life Safety   12/04/2020   Approved   DAVID HAENDLE
  Special Equipment   12/04/2020   Partial Approval   DAVID HAENDLE
  Life Safety   12/07/2020   Approved   DAVID HAENDLE
  Special Equipment   12/07/2020   No Access for Inspection   DAVID HAENDLE
  Life Safety   12/08/2020   Approved   DAVID HAENDLE
  Special Equipment   12/08/2020   Partial Approval   DAVID HAENDLE
  Special Equipment   12/09/2020   Corrections Issued   DAVID HAENDLE
  Special Equipment   12/09/2020   Off-Hour Fees Due   
  Special Equipment   12/10/2020   Off-Hour Fees Due   
  Special Equipment   12/10/2020   Partial Approval   DAVID HAENDLE
  Final   12/11/2020   Partial Approval   DAVID HAENDLE
  Special Equipment   12/11/2020   Partial Approval   DAVID HAENDLE
  Life Safety   12/15/2020   Approved   DAVID HAENDLE
  Special Equipment   12/15/2020   Not Ready for Inspection   DAVID HAENDLE
  Final   01/27/2021   Corrections Issued   DAVID HAENDLE
  Final   07/20/2021   Partial Approval   JOHNNY YUTRONICH
  Rough   12/01/2021   Conditional Approval   DAVID HAENDLE
  Service/Power Release   12/01/2021   Approved   DAVID HAENDLE
  Final   01/20/2022   Partial Inspection   MATTHEW COTTER
  Final   02/14/2022   Permit Finaled   MATTHEW COTTER