8424 W BEVERLY BLVD 90048
APPLICATION / PERMIT NUMBER: 14016-10000-23897
PLAN CHECK / JOB NUMBER: B14LA15990

Plan Check and Permit Information


GROUP: Building
TYPE: Bldg-Alter/Repair
SUB-TYPE: Commercial
PRIMARY USE: (17) Restaurant
WORK DESCRIPTION: REMODEL OF AN EXISTING BUILDING FOR (2) RESTARUANTS. add new storefront add outdoor eating area 12'1" x 30'. Hours of operation are from 7am- 11pm. Remove roof, walls, and footings at portion of the restaurant as per structural and architectural plans. Rebuild restaurant as per structural and architectural plans.
PERMIT ISSUED: Yes PERMIT ISSUE DATE: 04/22/2015 ISSUING OFFICE: Metro
CURRENT STATUS: CofO Issued CURRENT STATUS DATE: 05/26/2016

Permit Application Status History
Submitted 11/20/2014 APPLICANT
Disabled Access Plans Picked Up 12/04/2014 APPLICANT
Assigned to Plan Check Engineer 12/11/2014 ERIC CABRERA
Corrections Issued 12/15/2014 ERIC CABRERA
Green Plans Picked Up 12/15/2014 APPLICANT
Quality Review Completed 12/29/2014 BILL STUTSMAN
Building Plans Picked Up 01/07/2015 APPLICANT
Plan Check Approved 02/26/2015 ERIC CABRERA
Issued 04/22/2015 LADBS
CofO in Progress 05/12/2016 DAVID BURKHEAD
CofO Issued 05/26/2016 RICKEY JACKSON
Permit Finaled 05/26/2016 RICKEY JACKSON

Permit Application Clearance Information
Address approval Cleared 01/08/2015 RICHARD SOUTHERLAND
Eng Process Fee Ord 176,300 Cleared 01/08/2015 RICHARD SOUTHERLAND
Permit Cleared 01/08/2015 RICHARD SOUTHERLAND
Work Adjacent to Public Way Cleared 01/08/2015 DAVID PEREZ
Stormwater Pollution Mitigatn Cleared 01/16/2015 MICHAEL SCADUTO
Roof/Waste drainage to street Cleared 01/20/2015 RICHARD SOUTHERLAND
Sewer availability Cleared 01/20/2015 RICHARD SOUTHERLAND
Driveway location Cleared 01/30/2015 TAIMOUR TANAVOLI
Internal circulation Cleared 01/30/2015 TAIMOUR TANAVOLI
DAS Clearance Cleared 02/02/2015 SHINE LIN
Comm Cor/Mini-Mall Cleared 02/03/2015 ALFREDO PEREZ
ZA Case Cleared 02/03/2015 ALFREDO PEREZ
ZA Case Cleared 02/04/2015 ERIC CABRERA
Food Service Establishment Cleared 02/05/2015 WILFREDO VALDEZ
Green Code Cleared 02/19/2015 RUSSELL KELLY
Comm Cor/Mini-Mall Cleared 02/26/2015 VINCENT QUITORIANO
Food establishment approval Cleared 02/26/2015 LACDHS APPROVED

Licensed Professional/Contractor Information
Architect Information
Wick, David Sochu; Lic. No.: C29199
1820 ASHMORE PLACE
LOS ANGELES, CA  90026
Contractor Information
J G Construction; Lic. No.: 671997-B
15632 EL PRADO ROAD
CHINO, CA  91710
Engineer Information
Mills, Garrett Ward; Lic. No.: S5271
1276 E COLORADO BLVD STE 201
PASADENA, CA  91106

Inspection Activity Information

Inspector Information
ALFREDO LOPEZ, (213) 482-7361
Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspection Request(s)
  No data available

Inspection Request History
  Pre-Inspection   06/11/2015   Approved   DAVID BURKHEAD
  Footing/Foundation/Slab   08/14/2015   Partial Inspection   DAVID BURKHEAD
  Footing/Foundation/Slab   08/17/2015   Not Ready for Inspection   MICHAEL KUHN
  Deputy Reinf. Concrete   08/18/2015   Approved   MICHAEL KUHN
  Footing/Foundation/Slab   08/18/2015   Partial Approval   MICHAEL KUHN
  Deputy Reinf. Concrete   08/20/2015   Conditional Approval   DAVID BURKHEAD
  Green Building Rough   09/08/2015   Partial Inspection   ROLLIN GETTLE III
  METHANE-Rough   09/08/2015   Not Ready for Inspection   DAVID BURKHEAD
  Wood Frame   09/08/2015   Conditional Approval   DAVID BURKHEAD
  Footing/Foundation/Slab   09/15/2015   Not Ready for Inspection   GREGORY POMISH
  Footing/Foundation/Slab   09/17/2015   Partial Approval   DAVID BURKHEAD
  Excavation/Setback/Form/Re-Bar   09/24/2015   Partial Approval   DAVID BURKHEAD
  Special/Order Compliance   09/24/2015   Corrections Issued   DAVID BURKHEAD
  Floor/Roof Diaphrgm/Shear Wall   10/05/2015   Not Ready for Inspection   DAVID BURKHEAD
  Deputy Reinf. Concrete   10/06/2015   Conditional Approval   DAVID BURKHEAD
  Deputy Reinf. Concrete   10/13/2015   Approved   DAVID BURKHEAD
  Excavation/Setback/Form/Re-Bar   10/13/2015   Partial Approval   DAVID BURKHEAD
  Floor/Roof Diaphrgm/Shear Wall   10/13/2015   Partial Approval   DAVID BURKHEAD
  Floor/Roof Diaphrgm/Shear Wall   10/22/2015   Partial Approval   DAVID BURKHEAD
  Floor/Roof Diaphrgm/Shear Wall   10/27/2015   Partial Inspection   DAVID BURKHEAD
  Deputy Drilled-In Anchors   10/28/2015   Conditional Approval   DAVID BURKHEAD
  Excavation/Setback/Form/Re-Bar   10/29/2015   Not Ready for Inspection   GREGORY POMISH
  Footing/Foundation/Slab   10/29/2015   Not Ready for Inspection   GREGORY POMISH
  Deputy Wood Construction   10/30/2015   Conditional Approval   DAVID BURKHEAD
  Excavation/Setback/Form/Re-Bar   10/30/2015   Partial Approval   DAVID BURKHEAD
  Deputy Reinf. Concrete   11/02/2015   Conditional Approval   DAVID BURKHEAD
  Drywall Nailing   11/03/2015   Partial Approval   DAVID BURKHEAD
  Excavation/Setback/Form/Re-Bar   11/04/2015   Partial Approval   DAVID BURKHEAD
  Floor/Roof Diaphrgm/Shear Wall   11/10/2015   Partial Approval   DAVID BURKHEAD
  Deputy Reinf. Concrete   11/13/2015   Conditional Approval   DAVID BURKHEAD
  Excavation/Setback/Form/Re-Bar   11/13/2015   Partial Approval   DAVID BURKHEAD
  Drywall Nailing   11/23/2015   Partial Approval   DAVID BURKHEAD
  Green Building Rough   11/23/2015   Approved   ROLLIN GETTLE III
  Insulation   11/23/2015   Approved   DAVID BURKHEAD
  Drywall Nailing   12/01/2015   Partial Approval   DAVID BURKHEAD
  Interior/Exterior Lathing   12/01/2015   Approved   DAVID BURKHEAD
  Deputy Drilled-In Anchors   12/03/2015   Conditional Approval   DAVID BURKHEAD
  Drywall Nailing   12/04/2015   Not Ready for Inspection   DAVID BURKHEAD
  Drywall Nailing   12/07/2015   Partial Approval   DAVID BURKHEAD
  T-Bar Ceiling   12/15/2015   Approved   DAVID BURKHEAD
  Interior/Exterior Lathing   12/16/2015   Not Ready for Inspection   DAVID BURKHEAD
  Deputy Steel/Welding   12/18/2015   Approved   DAVID BURKHEAD
  Drywall Nailing   12/18/2015   Approved   DAVID BURKHEAD
  T-Bar Ceiling   01/15/2016   Partial Inspection   DAVID BURKHEAD
  METHANE-Rough   01/29/2016   Approved   DAVID BURKHEAD
  T-Bar Ceiling   01/29/2016   Approved   DAVID BURKHEAD
  Wood Frame   01/29/2016   Approved   DAVID BURKHEAD
  Deputy Reinf. Concrete   02/08/2016   Conditional Approval   DAVID BURKHEAD
  Excavation/Setback/Form/Re-Bar   02/08/2016   Approved   DAVID BURKHEAD
  Deputy Reinf. Concrete   02/09/2016   Conditional Approval   DAVID BURKHEAD
  Final   03/11/2016   Corrections Issued   DAVID BURKHEAD
  Green Building Final   03/11/2016   Not Ready for Inspection   MICKEY YAMASHITA
  SGSOV-Seismic Gas S/O Valve   03/11/2016   SGSOV Approved   DAVID BURKHEAD
  Smoke Detectors   03/11/2016   Approved   DAVID BURKHEAD
  Final   03/17/2016   Partial Inspection   DAVID BURKHEAD
  Green Building Final   03/18/2016   Corrections Issued   MICKEY YAMASHITA
  Final   03/29/2016   Partial Inspection   DAVID BURKHEAD
  Green Building Final   03/29/2016   Not Ready for Inspection   MICKEY YAMASHITA
  Green Building Final   04/01/2016   Approved   MICKEY YAMASHITA
  Final   05/12/2016   OK to Issue CofO   DAVID BURKHEAD