1601 N VINE ST 90028
APPLICATION / PERMIT NUMBER: 14010-10000-01878
PLAN CHECK / JOB NUMBER: B14LA08168

Plan Check and Permit Information


GROUP: Building
TYPE: Bldg-New
SUB-TYPE: Commercial
PRIMARY USE: (13) Office
WORK DESCRIPTION: 8--story core and shell office/retail building with 5 levels of subterranean parking.
PERMIT ISSUED: Yes PERMIT ISSUE DATE: 04/15/2015 ISSUING OFFICE: Metro
CURRENT STATUS: CofO Issued CURRENT STATUS DATE: 07/06/2017

Permit Application Status History
Submitted 06/19/2014 APPLICANT
Assigned to Plan Check Engineer 06/26/2014 ALLEN MANALANSAN
Disabled Access Plans Picked Up 07/03/2014 APPLICANT
Green Plans Picked Up 07/09/2014 APPLICANT
Corrections Issued 07/28/2014 ALLEN MANALANSAN
Quality Review Completed 07/28/2014 CHARLES CHANG
Building Plans Picked Up 07/29/2014 APPLICANT
Applicant returned to address corrections 08/22/2014 ALLEN MANALANSAN
Applicant returned to address corrections 09/04/2014 SAI KHUM
Applicant returned to address corrections 09/04/2014 ALLEN MANALANSAN
Applicant returned to address corrections 10/02/2014 SAI KHUM
Applicant returned to address corrections 10/02/2014 ALLEN MANALANSAN
Applicant returned to address corrections 10/07/2014 ALLEN MANALANSAN
Applicant returned to address corrections 10/07/2014 SAI KHUM
Applicant returned to address corrections 10/17/2014 ALLEN MANALANSAN
Plan Check Approved 04/15/2015 ALLEN MANALANSAN
Issued 04/15/2015 LADBS
CofO in Progress 07/06/2017 SAKO AGHAZARIAN
Permit Finaled 07/06/2017 HAMID PISHEHVAR
CofO Issued 07/06/2017 HAMID PISHEHVAR
Permit Finaled 07/06/2017 HAMID PISHEHVAR

Permit Application Clearance Information
Construction near power lines Cleared 07/03/2014 OSCAR CASTRO
Address approval Cleared 08/08/2014 VALENTINO PUEBLOS
City owned building/parcel Cleared 08/08/2014 HAROOT AVANESIAN
Encroachment in public way Cleared 08/08/2014 ARMANDO MEDINA
Eng Process Fee Ord 176,300 Cleared 08/08/2014 VALENTINO PUEBLOS
Building over 3-story or 36-ft Cleared 08/12/2014 CALOSHA APPROVED
City owned building/parcel Cleared 08/12/2014 HAROOT AVANESIAN
Excavation more than 5-ft deep Cleared 08/12/2014 CALOSHA APPROVED
Hydrant and Access approval Cleared 08/13/2014 ROBERT DUFF
ZI Cleared 08/25/2014 MARITZA PRZEKOP
Highway dedication Cleared 08/28/2014 LINDA MARGARET
Permit Cleared 08/28/2014 LINDA MARGARET
Roof/Waste drainage to street Cleared 08/28/2014 LINDA MARGARET
Miscellaneous Cleared 09/03/2014 LINDA MARGARET
Sewer availability Cleared 09/17/2014 DENNIS OROZCO
DAS Clearance Cleared 09/30/2014 WAI LAU
Low Impact Development Cleared 09/30/2014 AMMAR ELTAWIL
Stormwater Pollution Mitigatn Cleared 09/30/2014 AMMAR ELTAWIL
Hist. Property Cntrct Mgr Appr Cleared 10/02/2014 LAMBERT GIESSINGER
Historic monument Cleared 10/02/2014 LAMBERT GIESSINGER
Green Code Cleared 10/09/2014 DONALD CRICHLOW
Bicycle Parking Cleared 10/14/2014 CHRISTINE SOTELO
Fire Marshall Fire Life Safety Cleared 10/15/2014 ANDREW KO
Tract Map conditions Cleared 11/14/2014 HERMAN VAN BUREN
Transportation Demand Ord. Cleared 11/25/2014 TAIMOUR TANAVOLI
"D" conditions Cleared 12/01/2014 MARITZA PRZEKOP
ZA Case Cleared 12/01/2014 MARITZA PRZEKOP
Internal circulation Cleared 12/03/2014 TAIMOUR TANAVOLI
Work Adjacent to Public Way Cleared 12/04/2014 DAVID PEREZ
"Q" conditions Cleared 02/03/2015 MARITZA PRZEKOP
"T" removal Cleared 02/03/2015 MARITZA PRZEKOP
CPC Cleared 02/03/2015 MARITZA PRZEKOP
Site Plan review Cleared 02/03/2015 MARITZA PRZEKOP
Historical monument Cleared 03/25/2015 JIM URQUHART
Project located in CRA area Cleared 03/25/2015 JIM URQUHART

Licensed Professional/Contractor Information
Architect Information
Proctor, Curtis Robert; Lic. No.: C29637
120 VASSAR DR
C/O HARTMAN & MAJEWSKY DESIGN GROUP
ALBUQUERQUE, NM  87114
Contractor Information
Owner-Builder
  
Engineer Information
Hill, Edward Foster; Lic. No.: GE2126
GEOTECH 439 WESTERN AVE
GLENDALE, CA  91201
Engineer Information
Maingot, Martin Rex; Lic. No.: S5623
1605 ELMWOOD AVE
WILMETTE, IL  60091
Landscape Architect Information
Yamashita, Robert Osamu; Lic. No.: LA2008
16306 CALAHAN STREET
NORTH HILLS, CA  913433804

Inspection Activity Information

Inspector Information
DAVID BURKHEAD, (213) 276-8147
Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspection Request(s)
  No data available

Inspection Request History
  Deputy Reinf. Concrete   09/15/2015   Approved   SAKO AGHAZARIAN
  Deputy Shotcrete   09/29/2015   Approved   SAKO AGHAZARIAN
  Deputy Shotcrete   09/30/2015   Approved   SAKO AGHAZARIAN
  Footing/Foundation/Slab   10/02/2015   Partial Approval   SAKO AGHAZARIAN
  Verify Sprinkler Sign Off   10/02/2015   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   10/13/2015   Approved   SAKO AGHAZARIAN
  Footing/Foundation/Slab   10/13/2015   Partial Approval   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   10/14/2015   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   10/15/2015   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   10/16/2015   Approved   SAKO AGHAZARIAN
  Reinforced Concrete Frame   10/19/2015   Partial Approval   SAKO AGHAZARIAN
  Green Building Rough   10/26/2015   Not Ready for Inspection   JOHN KLARIN
  Reinforced Concrete Frame   10/26/2015   Partial Approval   SAKO AGHAZARIAN
  Reinforced Concrete Frame   11/02/2015   Partial Approval   SAKO AGHAZARIAN
  Deputy Shotcrete   11/03/2015   Approved   SAKO AGHAZARIAN
  Deputy Shotcrete   11/04/2015   Approved   SAKO AGHAZARIAN
  Deputy Shotcrete   11/05/2015   Approved   SAKO AGHAZARIAN
  Footing/Foundation/Slab   11/05/2015   Partial Approval   SAKO AGHAZARIAN
  Deputy Shotcrete   11/06/2015   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   11/10/2015   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   11/12/2015   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   11/13/2015   Conditional Approval   BARRY SILLS
  Footing/Foundation/Slab   11/17/2015   Partial Approval   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   12/07/2015   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   12/08/2015   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   12/09/2015   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   12/10/2015   Conditional Approval   BARRY SILLS
  Deputy Reinf. Concrete   12/11/2015   Conditional Approval   BARRY SILLS
  Special/Order Compliance   01/25/2016   Approved   STEPHEN REED
  Green Building Rough   02/04/2016   Not Ready for Inspection   JOHN KLARIN
  Reinforced Concrete Frame   02/04/2016   Partial Approval   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   02/08/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   02/09/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   02/10/2016   Approved   SAKO AGHAZARIAN
  Floor/Roof Diaphrgm/Shear Wall   02/10/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   02/11/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   02/12/2016   Approved   SAKO AGHAZARIAN
  Floor/Roof Diaphrgm/Shear Wall   02/16/2016   Partial Approval   SAKO AGHAZARIAN
  Deputy Drilled-In Anchors   02/22/2016   Approved   SAKO AGHAZARIAN
  Deputy Other (see comments)   02/22/2016   Approved   STEPHEN REED
  Deputy Reinf. Concrete   02/22/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   02/23/2016   Approved   SAKO AGHAZARIAN
  Footing/Foundation/Slab   02/26/2016   Partial Approval   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   02/29/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   03/01/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   03/02/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   03/03/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   03/04/2016   Approved   SAKO AGHAZARIAN
  Green Building Rough   03/09/2016   Not Ready for Inspection   MICKEY YAMASHITA
  Reinforced Concrete Frame   03/09/2016   Partial Approval   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   03/10/2016   Approved   SAKO AGHAZARIAN
  Deputy Shotcrete   03/17/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   03/22/2016   Conditional Approval   BARRY SILLS
  Reinforced Concrete Frame   03/22/2016   Partial Approval   BARRY SILLS
  Deputy Pre-Stress Concrete   03/23/2016   Conditional Approval   BARRY SILLS
  Deputy Reinf. Concrete   03/23/2016   Conditional Approval   BARRY SILLS
  Deputy Drilled-In Anchors   03/31/2016   Approved   SAKO AGHAZARIAN
  Deputy Drilled-In Anchors   04/01/2016   Approved   SAKO AGHAZARIAN
  Reinforced Concrete Frame   04/06/2016   Partial Approval   SAKO AGHAZARIAN
  Deputy Shotcrete   04/13/2016   Approved   SAKO AGHAZARIAN
  Deputy Shotcrete   04/14/2016   Approved   SAKO AGHAZARIAN
  Reinforced Concrete Frame   04/14/2016   Partial Approval   SAKO AGHAZARIAN
  Deputy Shotcrete   04/15/2016   Approved   SAKO AGHAZARIAN
  Deputy Pre-Stress Concrete   04/18/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   04/18/2016   Approved   SAKO AGHAZARIAN
  Deputy Pre-Stress Concrete   04/19/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   04/19/2016   Approved   SAKO AGHAZARIAN
  Deputy Pre-Stress Concrete   04/20/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   04/20/2016   Approved   SAKO AGHAZARIAN
  Deputy Pre-Stress Concrete   04/21/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   04/21/2016   Approved   SAKO AGHAZARIAN
  Reinforced Concrete Frame   04/21/2016   Partial Approval   SAKO AGHAZARIAN
  Deputy Pre-Stress Concrete   04/22/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   04/22/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   04/22/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   04/29/2016   Approved   SAKO AGHAZARIAN
  Deputy Drilled-In Anchors   05/02/2016   Approved   SAKO AGHAZARIAN
  Deputy Pre-Stress Concrete   05/02/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   05/02/2016   Approved   SAKO AGHAZARIAN
  Deputy Drilled-In Anchors   05/03/2016   Approved   SAKO AGHAZARIAN
  Deputy Pre-Stress Concrete   05/03/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   05/03/2016   Approved   SAKO AGHAZARIAN
  Deputy Drilled-In Anchors   05/04/2016   Approved   SAKO AGHAZARIAN
  Deputy Pre-Stress Concrete   05/04/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   05/04/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   05/04/2016   Approved   SAKO AGHAZARIAN
  Reinforced Concrete Frame   05/04/2016   Partial Approval   SAKO AGHAZARIAN
  Deputy Drilled-In Anchors   05/05/2016   Approved   SAKO AGHAZARIAN
  Deputy Pre-Stress Concrete   05/05/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   05/05/2016   Approved   SAKO AGHAZARIAN
  Deputy Drilled-In Anchors   05/06/2016   Approved   SAKO AGHAZARIAN
  Deputy Pre-Stress Concrete   05/06/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   05/06/2016   Approved   SAKO AGHAZARIAN
  Deputy Drilled-In Anchors   05/10/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Masonry   05/10/2016   Approved   SAKO AGHAZARIAN
  Deputy Shotcrete   05/10/2016   Approved   SAKO AGHAZARIAN
  Deputy Drilled-In Anchors   05/11/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Masonry   05/11/2016   Approved   SAKO AGHAZARIAN
  Deputy Shotcrete   05/11/2016   Approved   SAKO AGHAZARIAN
  Deputy Drilled-In Anchors   05/12/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Masonry   05/12/2016   Approved   SAKO AGHAZARIAN
  Deputy Shotcrete   05/12/2016   Approved   SAKO AGHAZARIAN
  Deputy Drilled-In Anchors   05/13/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Masonry   05/13/2016   Approved   SAKO AGHAZARIAN
  Deputy Shotcrete   05/13/2016   Approved   SAKO AGHAZARIAN
  Deputy Shotcrete   05/16/2016   Approved   SAKO AGHAZARIAN
  Reinforced Concrete Frame   05/16/2016   Partial Approval   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   05/17/2016   Approved   SAKO AGHAZARIAN
  Deputy Shotcrete   05/17/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   05/18/2016   Approved   SAKO AGHAZARIAN
  Reinforced Concrete Frame   05/25/2016   Partial Approval   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   05/26/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   05/27/2016   Approved   SAKO AGHAZARIAN
  Light Gage Steel Frame   05/27/2016   Partial Inspection   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   05/31/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   06/01/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   06/01/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   06/02/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   06/02/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   06/03/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   06/03/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   06/06/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   06/07/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   06/07/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   06/08/2016   Conditional Approval   BARRY SILLS
  Deputy Reinf. Concrete   06/09/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   06/10/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   06/13/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Masonry   06/13/2016   Approved   SAKO AGHAZARIAN
  Reinforced Concrete Frame   06/13/2016   Partial Approval   SAKO AGHAZARIAN
  Reinforced Masonry Frame   06/13/2016   Partial Approval   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   06/14/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   06/15/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   06/16/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   06/17/2016   Approved   SAKO AGHAZARIAN
  Reinforced Masonry Frame   06/21/2016   Partial Approval   SAKO AGHAZARIAN
  Deputy Steel/Welding   06/27/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   06/28/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   06/29/2016   Approved   SAKO AGHAZARIAN
  Reinforced Concrete Frame   06/29/2016   Partial Approval   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   06/30/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   06/30/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   07/01/2016   Approved   SAKO AGHAZARIAN
  Drywall Nailing   07/07/2016   Partial Inspection   SAKO AGHAZARIAN
  Light Gage Steel Frame   07/08/2016   Partial Inspection   SAKO AGHAZARIAN
  Deputy Steel/Welding   07/18/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   07/19/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   07/20/2016   Approved   SAKO AGHAZARIAN
  Reinforced Concrete Frame   07/20/2016   Partial Approval   SAKO AGHAZARIAN
  Deputy Steel/Welding   07/21/2016   Conditional Approval   BARRY SILLS
  Deputy Steel/Welding   07/22/2016   Conditional Approval   BARRY SILLS
  Drywall Nailing   08/03/2016   Partial Inspection   SAKO AGHAZARIAN
  Deputy Steel/Welding   08/09/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   08/10/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   08/11/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   08/12/2016   Approved   SAKO AGHAZARIAN
  Light Gage Steel Frame   08/16/2016   Partial Inspection   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   08/19/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   08/23/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   08/24/2016   Approved   SAKO AGHAZARIAN
  Drywall Nailing   08/24/2016   Partial Approval   SAKO AGHAZARIAN
  Deputy Steel/Welding   08/25/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   08/26/2016   Approved   SAKO AGHAZARIAN
  Green Building Final   09/01/2016   Partial Inspection   DONALD CRICHLOW
  Green Building Rough   09/01/2016   Not Ready for Inspection   DONALD CRICHLOW
  Deputy Steel/Welding   09/06/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   09/07/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Masonry   09/08/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   09/08/2016   Approved   SAKO AGHAZARIAN
  Drywall Nailing   09/08/2016   Partial Approval   SAKO AGHAZARIAN
  Deputy Steel/Welding   09/09/2016   Conditional Approval   BARRY SILLS
  Light Gage Steel Frame   09/19/2016   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   09/20/2016   Partial Approval   SAKO AGHAZARIAN
  Deputy Steel/Welding   09/22/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   09/23/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   09/26/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   09/27/2016   Approved   SAKO AGHAZARIAN
  Interior/Exterior Lathing   09/27/2016   Partial Inspection   SAKO AGHAZARIAN
  Light Gage Steel Frame   09/27/2016   Partial Approval   SAKO AGHAZARIAN
  Deputy Steel/Welding   09/28/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   09/29/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   09/30/2016   Approved   SAKO AGHAZARIAN
  Light Gage Steel Frame   10/04/2016   Partial Approval   SAKO AGHAZARIAN
  Deputy Steel/Welding   10/05/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   10/06/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   10/07/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   10/13/2016   Approved   SAKO AGHAZARIAN
  Reinforced Concrete Frame   10/13/2016   Partial Approval   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   10/18/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   10/20/2016   Approved   SAKO AGHAZARIAN
  Green Building Rough   10/20/2016   Not Ready for Inspection   MICKEY YAMASHITA
  Reinforced Concrete Frame   10/20/2016   Partial Approval   SAKO AGHAZARIAN
  Deputy Drilled-In Anchors   10/25/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   10/25/2016   Approved   SAKO AGHAZARIAN
  Deputy Drilled-In Anchors   10/26/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   10/26/2016   Approved   SAKO AGHAZARIAN
  Deputy Drilled-In Anchors   10/27/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   10/27/2016   Approved   SAKO AGHAZARIAN
  T-Bar Ceiling   10/27/2016   Approved   SAKO AGHAZARIAN
  Deputy Drilled-In Anchors   10/28/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   10/28/2016   Approved   SAKO AGHAZARIAN
  Light Gage Steel Frame   11/03/2016   Approved   SAKO AGHAZARIAN
  Structural Steel Frame   11/03/2016   Partial Approval   SAKO AGHAZARIAN
  Insulation   11/10/2016   Approved   SAKO AGHAZARIAN
  Light Gage Steel Frame   11/10/2016   Partial Approval   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   12/19/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   12/19/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   12/20/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   12/20/2016   Approved   SAKO AGHAZARIAN
  Light Gage Steel Frame   12/20/2016   Partial Approval   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   12/21/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   12/21/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   12/22/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   12/22/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   12/23/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   12/23/2016   Approved   SAKO AGHAZARIAN
  Light Gage Steel Frame   12/28/2016   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   01/04/2017   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   01/05/2017   Approved   SAKO AGHAZARIAN
  Deputy Steel/Welding   01/06/2017   Conditional Approval   BARRY SILLS
  Light Gage Steel Frame   01/19/2017   Partial Approval   SAKO AGHAZARIAN
  Drywall Nailing   02/08/2017   Partial Inspection   SAKO AGHAZARIAN
  Light Gage Steel Frame   02/08/2017   Approved   SAKO AGHAZARIAN
  Light Gage Steel Frame   03/10/2017   Approved   SAKO AGHAZARIAN
  Light Gage Steel Frame   03/17/2017   Partial Inspection   SAKO AGHAZARIAN
  Drywall Nailing   04/03/2017   Partial Inspection   SAKO AGHAZARIAN
  Final   04/03/2017   Partial Inspection   SAKO AGHAZARIAN
  Footing/Foundation/Slab   04/03/2017   Approved   SAKO AGHAZARIAN
  Green Building Final   04/03/2017   Not Ready for Inspection   WILLIAM ROSE
  Green Building Rough   04/03/2017   Conditional Approval   WILLIAM ROSE
  Reinforced Concrete Frame   04/03/2017   Approved   SAKO AGHAZARIAN
  SGSOV-Seismic Gas S/O Valve   04/03/2017   SGSOV Approved   SAKO AGHAZARIAN
  Smoke Detectors   04/03/2017   Approved   SAKO AGHAZARIAN
  Green Building Rough   04/25/2017   Partial Approval   WILLIAM ROSE
  Green Building Final   04/26/2017   Not Ready for Inspection   WILLIAM ROSE
  Drywall Nailing   04/27/2017   Partial Approval   SAKO AGHAZARIAN
  Final   04/27/2017   Partial Inspection   SAKO AGHAZARIAN
  Green Building Rough   04/27/2017   Approved   WILLIAM ROSE
  Reinforced Concrete Frame   04/27/2017   Approved   SAKO AGHAZARIAN
  Green Building Final   06/19/2017   Not Ready for Inspection   WILLIAM ROSE
  Green Building Final   06/21/2017   Approved   WILLIAM ROSE
  Drywall Nailing   06/26/2017   Approved   SAKO AGHAZARIAN
  Final   06/26/2017   Partial Inspection   SAKO AGHAZARIAN
  Final   07/06/2017   OK to Issue CofO   SAKO AGHAZARIAN