Submitted |
03/24/2014 |
APPLICANT |
Assigned to Plan Check Engineer |
03/27/2014 |
SUEN LIEU |
Corrections Issued |
04/10/2014 |
MINYE PAK |
Quality Review Completed |
04/10/2014 |
SUEN LIEU |
Building Plans Picked Up |
04/11/2014 |
APPLICANT |
Applicant returned to address corrections |
05/07/2014 |
SUEN LIEU |
Applicant returned to address corrections |
05/07/2014 |
MINYE PAK |
Applicant returned to address corrections |
05/29/2014 |
SUEN LIEU |
Applicant returned to address corrections |
05/29/2014 |
MINYE PAK |
Applicant returned to address corrections |
06/02/2014 |
MINYE PAK |
Applicant returned to address corrections |
06/11/2014 |
SUEN LIEU |
Applicant returned to address corrections |
06/11/2014 |
MINYE PAK |
Applicant returned to address corrections |
07/07/2014 |
CHARLES CHANG |
Applicant returned to address corrections |
07/09/2014 |
CHARLES CHANG |
Applicant returned to address corrections |
07/10/2014 |
CHARLES CHANG |
Applicant returned to address corrections |
07/17/2014 |
SUEN LIEU |
Applicant returned to address corrections |
08/21/2014 |
SUEN LIEU |
Applicant returned to address corrections |
09/12/2014 |
SUEN LIEU |
Applicant returned to address corrections |
11/20/2014 |
SUEN LIEU |
Applicant returned to address corrections |
11/21/2014 |
SUEN LIEU |
Applicant returned to address corrections |
11/25/2014 |
SUEN LIEU |
Applicant returned to address corrections |
02/20/2015 |
SUEN LIEU |
Applicant returned to address corrections |
02/24/2015 |
SUEN LIEU |
Applicant returned to address corrections |
03/24/2015 |
SUEN LIEU |
Applicant returned to address corrections |
04/09/2015 |
SUEN LIEU |
Applicant returned to address corrections |
05/11/2015 |
SUEN LIEU |
Applicant returned to address corrections |
07/06/2015 |
SUEN LIEU |
Applicant returned to address corrections |
08/14/2015 |
SUEN LIEU |
Applicant returned to address corrections |
08/17/2015 |
SUEN LIEU |
Applicant returned to address corrections |
09/29/2015 |
SUEN LIEU |
Applicant returned to address corrections |
10/05/2015 |
SUEN LIEU |
Applicant returned to address corrections |
12/07/2015 |
SUEN LIEU |
Applicant returned to address corrections |
07/21/2016 |
SUEN LIEU |
Applicant returned to address corrections |
08/26/2016 |
SUEN LIEU |
Applicant returned to address corrections |
12/01/2016 |
SUEN LIEU |
Applicant returned to address corrections |
12/19/2016 |
SUEN LIEU |
Applicant returned to address corrections |
12/21/2016 |
SUEN LIEU |
Applicant returned to address corrections |
12/22/2016 |
SUEN LIEU |
Applicant returned to address corrections |
01/05/2017 |
SUEN LIEU |
Applicant returned to address corrections |
01/20/2017 |
SUEN LIEU |
Applicant returned to address corrections |
01/26/2017 |
SUEN LIEU |
Applicant returned to address corrections |
01/31/2017 |
MINYE PAK |
Applicant returned to address corrections |
02/03/2017 |
SUEN LIEU |
Applicant returned to address corrections |
02/07/2017 |
SUEN LIEU |
Applicant returned to address corrections |
02/14/2017 |
MINYE PAK |
Applicant returned to address corrections |
02/17/2017 |
SUEN LIEU |
Applicant returned to address corrections |
02/23/2017 |
SUEN LIEU |
Plan Check Approved |
03/03/2017 |
MINYE PAK |
Issued |
03/06/2017 |
LADBS |
CofO in Progress |
12/19/2023 |
EDWIN GREGORYONA |
Permit Finaled |
03/09/2024 |
ADAM BURGESS |
CofO Issued |
03/09/2024 |
ADAM BURGESS |
Permit Finaled |
03/09/2024 |
ADAM BURGESS |
Address approval |
Cleared |
03/28/2014 |
VALENTINO PUEBLOS |
"D" conditions |
Cleared |
05/12/2014 |
MARITZA PRZEKOP |
"Q" conditions |
Cleared |
05/12/2014 |
MARITZA PRZEKOP |
Site Plan review |
Cleared |
05/12/2014 |
MARITZA PRZEKOP |
Eng Process Fee Ord 176,300 |
Cleared |
09/26/2014 |
VALENTINO PUEBLOS |
Permit |
Cleared |
09/26/2014 |
VALENTINO PUEBLOS |
Hydrant and Access approval |
Cleared |
10/15/2014 |
ROBERT DUFF |
Driveway location |
Cleared |
10/24/2014 |
TAIMOUR TANAVOLI |
Transportation Demand Ord. |
Cleared |
10/24/2014 |
TAIMOUR TANAVOLI |
Highway dedication |
Cleared |
10/31/2014 |
VALENTINO PUEBLOS |
Miscellaneous |
Cleared |
10/31/2014 |
VALENTINO PUEBLOS |
Roof/Waste drainage to street |
Cleared |
10/31/2014 |
VALENTINO PUEBLOS |
DAS Clearance |
Cleared |
11/25/2014 |
MINYE PAK |
"D" conditions |
Cleared |
01/22/2015 |
MARITZA PRZEKOP |
Sewer availability |
Cleared |
02/02/2015 |
VALENTINO PUEBLOS |
"D" conditions |
Cleared |
12/21/2016 |
MARITZA PRZEKOP |
Work Adjacent to Public Way |
Cleared |
01/18/2017 |
TERRY PHAN |
Building over 3-story or 36-ft |
Cleared |
01/31/2017 |
CALOSHA APPROVED |
Excavation more than 5-ft deep |
Cleared |
01/31/2017 |
CALOSHA APPROVED |
Green Code |
Cleared |
02/09/2017 |
MICKEY YAMASHITA |
Building over 3-story or 36-ft |
Cleared |
02/14/2017 |
CALOSHA APPROVED |
Excavation more than 5-ft deep |
Cleared |
02/14/2017 |
CALOSHA APPROVED |
Title 19 building approval |
Cleared |
03/01/2017 |
DAVE MYERS |
Metro Rail approval |
Cleared |
03/03/2017 |
ASPET DAVIDIAN |
Low Impact Development |
Cleared |
03/06/2017 |
AMMAR ELTAWIL |