Los Angeles department of building safty logo Permit and Inspection Report banner
5790 W JEFFERSON BLVD 90016
APPLICATION / PERMIT NUMBER: 14010-10000-00780
PLAN CHECK / JOB NUMBER: B14LA02928

Plan Check and Permit Information


GROUP: Building
TYPE: Bldg-New
SUB-TYPE: Commercial
PRIMARY USE: (13) Office
WORK DESCRIPTION: NEW 16 STORY HIGHRISE OFFICE BUILDING WITH PARKING AT 2 SUBTERRANEAN LEVELS AND GROUND FLOOR.
PERMIT ISSUED: Yes PERMIT ISSUE DATE: 03/06/2017 ISSUING OFFICE: Metro
CURRENT STATUS: CofO Issued CURRENT STATUS DATE: 03/09/2024

Permit Application Status History
Submitted 03/24/2014 APPLICANT
Assigned to Plan Check Engineer 03/27/2014 SUEN LIEU
Corrections Issued 04/10/2014 MINYE PAK
Quality Review Completed 04/10/2014 SUEN LIEU
Building Plans Picked Up 04/11/2014 APPLICANT
Applicant returned to address corrections 05/07/2014 SUEN LIEU
Applicant returned to address corrections 05/07/2014 MINYE PAK
Applicant returned to address corrections 05/29/2014 SUEN LIEU
Applicant returned to address corrections 05/29/2014 MINYE PAK
Applicant returned to address corrections 06/02/2014 MINYE PAK
Applicant returned to address corrections 06/11/2014 SUEN LIEU
Applicant returned to address corrections 06/11/2014 MINYE PAK
Applicant returned to address corrections 07/07/2014 CHARLES CHANG
Applicant returned to address corrections 07/09/2014 CHARLES CHANG
Applicant returned to address corrections 07/10/2014 CHARLES CHANG
Applicant returned to address corrections 07/17/2014 SUEN LIEU
Applicant returned to address corrections 08/21/2014 SUEN LIEU
Applicant returned to address corrections 09/12/2014 SUEN LIEU
Applicant returned to address corrections 11/20/2014 SUEN LIEU
Applicant returned to address corrections 11/21/2014 SUEN LIEU
Applicant returned to address corrections 11/25/2014 SUEN LIEU
Applicant returned to address corrections 02/20/2015 SUEN LIEU
Applicant returned to address corrections 02/24/2015 SUEN LIEU
Applicant returned to address corrections 03/24/2015 SUEN LIEU
Applicant returned to address corrections 04/09/2015 SUEN LIEU
Applicant returned to address corrections 05/11/2015 SUEN LIEU
Applicant returned to address corrections 07/06/2015 SUEN LIEU
Applicant returned to address corrections 08/14/2015 SUEN LIEU
Applicant returned to address corrections 08/17/2015 SUEN LIEU
Applicant returned to address corrections 09/29/2015 SUEN LIEU
Applicant returned to address corrections 10/05/2015 SUEN LIEU
Applicant returned to address corrections 12/07/2015 SUEN LIEU
Applicant returned to address corrections 07/21/2016 SUEN LIEU
Applicant returned to address corrections 08/26/2016 SUEN LIEU
Applicant returned to address corrections 12/01/2016 SUEN LIEU
Applicant returned to address corrections 12/19/2016 SUEN LIEU
Applicant returned to address corrections 12/21/2016 SUEN LIEU
Applicant returned to address corrections 12/22/2016 SUEN LIEU
Applicant returned to address corrections 01/05/2017 SUEN LIEU
Applicant returned to address corrections 01/20/2017 SUEN LIEU
Applicant returned to address corrections 01/26/2017 SUEN LIEU
Applicant returned to address corrections 01/31/2017 MINYE PAK
Applicant returned to address corrections 02/03/2017 SUEN LIEU
Applicant returned to address corrections 02/07/2017 SUEN LIEU
Applicant returned to address corrections 02/14/2017 MINYE PAK
Applicant returned to address corrections 02/17/2017 SUEN LIEU
Applicant returned to address corrections 02/23/2017 SUEN LIEU
Plan Check Approved 03/03/2017 MINYE PAK
Issued 03/06/2017 LADBS
CofO in Progress 12/19/2023 EDWIN GREGORYONA
Permit Finaled 03/09/2024 ADAM BURGESS
CofO Issued 03/09/2024 ADAM BURGESS
Permit Finaled 03/09/2024 ADAM BURGESS

Permit Application Clearance Information
Address approval Cleared 03/28/2014 VALENTINO PUEBLOS
"D" conditions Cleared 05/12/2014 MARITZA PRZEKOP
"Q" conditions Cleared 05/12/2014 MARITZA PRZEKOP
Site Plan review Cleared 05/12/2014 MARITZA PRZEKOP
Eng Process Fee Ord 176,300 Cleared 09/26/2014 VALENTINO PUEBLOS
Permit Cleared 09/26/2014 VALENTINO PUEBLOS
Hydrant and Access approval Cleared 10/15/2014 ROBERT DUFF
Driveway location Cleared 10/24/2014 TAIMOUR TANAVOLI
Transportation Demand Ord. Cleared 10/24/2014 TAIMOUR TANAVOLI
Highway dedication Cleared 10/31/2014 VALENTINO PUEBLOS
Miscellaneous Cleared 10/31/2014 VALENTINO PUEBLOS
Roof/Waste drainage to street Cleared 10/31/2014 VALENTINO PUEBLOS
DAS Clearance Cleared 11/25/2014 MINYE PAK
"D" conditions Cleared 01/22/2015 MARITZA PRZEKOP
Sewer availability Cleared 02/02/2015 VALENTINO PUEBLOS
"D" conditions Cleared 12/21/2016 MARITZA PRZEKOP
Work Adjacent to Public Way Cleared 01/18/2017 TERRY PHAN
Building over 3-story or 36-ft Cleared 01/31/2017 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 01/31/2017 CALOSHA APPROVED
Green Code Cleared 02/09/2017 MICKEY YAMASHITA
Building over 3-story or 36-ft Cleared 02/14/2017 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 02/14/2017 CALOSHA APPROVED
Title 19 building approval Cleared 03/01/2017 DAVE MYERS
Metro Rail approval Cleared 03/03/2017 ASPET DAVIDIAN
Low Impact Development Cleared 03/06/2017 AMMAR ELTAWIL

Licensed Professional/Contractor Information
Architect Information
Moss, Eric Owen; Lic. No.: C8408
8557 HIGUERA ST.
CULVER CITY, CA  90232
Contractor Information
Matt Construction Corporation; Lic. No.: 631020-B
9814 NORWALK BLVD #100
SANTA FE SPRINGS, CA  90670
Engineer Information
Jordan, Ricardo; Lic. No.: C68436
5937 DARWIN CT STE 105
CARLSBAD, CA  92008
Engineer Information
Kirby, Anthony David; Lic. No.: C79357
12777 WEST JEFFERSON BLVD STE 200
LOS ANGELES, CA  90066
Engineer Information
Lew, Marshall; Lic. No.: GE522
700 FLORES DE ORO
SOUTH PASADENA, CA  910303635
Engineer Information
Ponnaboyina, Hari; Lic. No.: C75269
3509 EAST ANDY ST
LONG BEACH, CA  90805
Engineer Information
Zekioglu, Atila; Lic. No.: S3455
12777 W JEFFERSON BL 200
LOS ANGELES, CA  90066
Geologist Information
Elliott, Paul James; Lic. No.: EG1435
25410 BAYSIDE PLACE
HARBOR CITY, CA  90710

Inspection Activity Information

Inspector Information
EDWIN GREGORYONA, (213) 482-7357
Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspection Request(s)
  No data available

Inspection Request History
  Pre-Inspection   04/25/2018   Partial Inspection   GREGORY POMISH
  Deputy Reinf. Concrete   12/13/2018   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   03/29/2019   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   04/01/2019   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   04/03/2019   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   04/03/2019   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   05/01/2019   Partial Approval   JAMES POWERS
  Deputy Reinf. Concrete   05/13/2019   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   06/14/2019   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   08/26/2019   Partial Approval   JAMES POWERS
  Deputy Reinf. Concrete   09/03/2019   Conditional Approval   WINSTON DUNNING
  Excavation/Setback/Form/Re-Bar   10/09/2019   Partial Approval   JAMES POWERS
  Green Building Rough   10/10/2019   Not Ready for Inspection   JAMES POWERS
  Reinforced Concrete Frame   10/10/2019   Partial Approval   JAMES POWERS
  Verify Sprinkler Sign Off   10/10/2019   Not Ready for Inspection   JAMES POWERS
  Deputy Reinf. Concrete   10/11/2019   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   10/30/2019   Approved   JEFF BYTHEWAY
  Deputy Reinf. Concrete   11/07/2019   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   12/18/2019   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   12/19/2019   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   12/20/2019   Partial Approval   JAMES POWERS
  Deputy Steel/Welding   12/23/2019   Partial Approval   JAMES POWERS
  Deputy Steel/Welding   12/24/2019   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   12/26/2019   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   12/27/2019   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   12/30/2019   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   12/31/2019   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/02/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/03/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/06/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/07/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/08/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/09/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/10/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/13/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/14/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/15/2020   Approved   HAMID PISHEHVAR
  Deputy Steel/Welding   01/16/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/17/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/21/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/22/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/23/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/24/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/27/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/28/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/29/2020   Partial Approval   JAMES POWERS
  Deputy Steel/Welding   01/30/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/31/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   02/03/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   02/04/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   02/05/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   02/06/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   02/07/2020   Conditional Approval   JONATHAN QUACH
  Deputy Steel/Welding   02/11/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   02/12/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   02/13/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   02/14/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   02/18/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   02/19/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   02/20/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   02/21/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   02/24/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   02/24/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   02/25/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   02/25/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   02/26/2020   Partial Approval   JAMES POWERS
  Deputy Steel/Welding   02/26/2020   Partial Approval   JAMES POWERS
  Deputy Reinf. Concrete   02/27/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   02/27/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   02/28/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   02/28/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   03/02/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   03/02/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   03/03/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   03/03/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   03/04/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   03/05/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   03/06/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   03/09/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   03/10/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   03/11/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   03/11/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   03/12/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   03/13/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   03/13/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   03/16/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   03/16/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   03/17/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   03/18/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   03/18/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   03/19/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   03/20/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   03/20/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   03/23/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   03/23/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   03/24/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   03/24/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   03/25/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   03/25/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   03/26/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   03/26/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   03/27/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   03/27/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   03/31/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   03/31/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   04/01/2020   Approved   LARRY ARNICK
  Deputy Steel/Welding   04/01/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   04/02/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   04/02/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   04/03/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   04/06/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   04/06/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   04/07/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   04/07/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   04/08/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   04/08/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   04/09/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   04/09/2020   Approved   LARRY ARNICK
  Deputy Steel/Welding   04/09/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   04/10/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   04/10/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   04/13/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   04/13/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   04/14/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   04/14/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   04/15/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   04/15/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   04/16/2020   Conditional Approval   JONATHAN QUACH
  Deputy Steel/Welding   04/16/2020   Conditional Approval   JONATHAN QUACH
  Deputy Reinf. Concrete   04/17/2020   Conditional Approval   JONATHAN QUACH
  Deputy Steel/Welding   04/17/2020   Conditional Approval   JONATHAN QUACH
  Deputy Steel/Welding   04/20/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   04/21/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   04/22/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   04/23/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   04/24/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   04/27/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   04/29/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   04/30/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   05/01/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   05/04/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   05/05/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   05/06/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   05/07/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   05/08/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   05/08/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   05/11/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   05/12/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   05/13/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   05/14/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   05/15/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   05/19/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   05/19/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   05/20/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   05/21/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   05/22/2020   Partial Approval   JAMES POWERS
  Deputy Steel/Welding   05/27/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   05/28/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   05/29/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   06/02/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   06/03/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   06/04/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   06/08/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   06/08/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   06/10/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   06/11/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   06/12/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   06/15/2020   Partial Approval   JAMES POWERS
  Deputy Steel/Welding   06/16/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   06/17/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   06/18/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   06/19/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   06/22/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   06/23/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   06/24/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   06/25/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   06/26/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   06/29/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   06/30/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   07/02/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   07/09/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   07/09/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   07/10/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   07/13/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   07/14/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   07/15/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   07/17/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   07/20/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   07/21/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   07/22/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   07/23/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   07/24/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   07/27/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   07/28/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   07/28/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   07/29/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   07/30/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   07/31/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   08/03/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   08/05/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   08/06/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   08/07/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   08/10/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   08/11/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   08/12/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   08/13/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   08/14/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   08/17/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   08/18/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   08/19/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   08/19/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   08/24/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   08/24/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   08/25/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   08/26/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   08/26/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   08/27/2020   Conditional Approval   JONATHAN QUACH
  Deputy Steel/Welding   08/28/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   08/31/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   09/01/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   09/02/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   09/02/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   09/03/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   09/10/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   09/11/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   09/14/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   09/15/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   09/16/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   09/16/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   09/17/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   09/21/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   09/22/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   09/23/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   09/24/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   09/25/2020   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   09/28/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   09/29/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   09/30/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   10/01/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   10/02/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   10/05/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   10/08/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   10/09/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   10/13/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   10/14/2020   Partial Approval   JAMES POWERS
  Deputy Steel/Welding   10/15/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   10/16/2020   Conditional Approval   DAVID BURKHEAD
  Deputy Steel/Welding   10/19/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   10/20/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   10/21/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   10/27/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   10/28/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   10/29/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   10/30/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   11/02/2020   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   11/05/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   11/06/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   11/09/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   11/10/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   11/16/2020   Approved   DANIEL MC AULIFFE
  Deputy Steel/Welding   11/18/2020   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   11/19/2020   Partial Approval   EDWIN GREGORYONA
  Deputy Reinf. Concrete   11/20/2020   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   11/20/2020   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   11/23/2020   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   11/24/2020   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   11/30/2020   Conditional Approval   DANIEL COLLINS
  Deputy Steel/Welding   12/01/2020   Conditional Approval   RAFAEL ESPINOZA
  Deputy Steel/Welding   12/02/2020   Partial Approval   JAMES POWERS
  Deputy Steel/Welding   12/03/2020   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   12/04/2020   Partial Approval   JAMES POWERS
  Deputy Steel/Welding   12/07/2020   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   12/08/2020   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   12/10/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   12/11/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   12/14/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   12/15/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   12/16/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   12/17/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   12/18/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   12/21/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   12/22/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   12/23/2020   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/04/2021   Partial Approval   JAMES POWERS
  Deputy Steel/Welding   01/05/2021   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/06/2021   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/07/2021   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/08/2021   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/11/2021   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/12/2021   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/13/2021   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/14/2021   Conditional Approval   LARRY ARNICK
  Deputy Reinf. Concrete   01/15/2021   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/15/2021   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/20/2021   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/21/2021   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/22/2021   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/25/2021   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/26/2021   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/28/2021   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   01/29/2021   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   02/01/2021   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   02/02/2021   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   02/03/2021   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   02/04/2021   Conditional Approval   LARRY ARNICK
  Deputy Steel/Welding   02/05/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   02/08/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   02/09/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   02/10/2021   Conditional Approval   TIMOTHY BUXTON
  Deputy Steel/Welding   02/11/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   02/12/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   02/16/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   02/17/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   02/18/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   02/19/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   02/22/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   02/23/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   02/24/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   02/25/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   02/26/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   03/01/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   03/02/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   03/03/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   03/04/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   03/05/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   03/08/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   03/09/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   03/10/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   03/11/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   03/12/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   03/15/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   03/18/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   03/19/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   03/22/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   03/23/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   03/24/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   03/25/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   03/26/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   03/30/2021   Partial Approval   EDWIN GREGORYONA
  Footing/Foundation/Slab   03/30/2021   Partial Approval   EDWIN GREGORYONA
  Green Building Rough   03/30/2021   Not Ready for Inspection   EDWIN GREGORYONA
  Verify Sprinkler Sign Off   03/30/2021   Not Ready for Inspection   EDWIN GREGORYONA
  Deputy Reinf. Concrete   03/31/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   03/31/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   04/01/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   04/05/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   04/06/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   04/07/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   04/08/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   04/09/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   04/12/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   04/13/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   04/14/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   04/15/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   04/16/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   04/19/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   04/20/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   04/21/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   04/22/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   04/23/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   04/26/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   04/27/2021   Partial Approval   EDWIN GREGORYONA
  Footing/Foundation/Slab   04/27/2021   Partial Approval   EDWIN GREGORYONA
  Green Building Rough   04/27/2021   Partial Inspection   EDWIN GREGORYONA
  Verify Sprinkler Sign Off   04/27/2021   Partial Inspection   EDWIN GREGORYONA
  Deputy Reinf. Concrete   04/28/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   04/28/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   04/29/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   04/30/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   05/03/2021   Conditional Approval   DAVID BURKHEAD
  Deputy Steel/Welding   05/04/2021   Partial Approval   EDWIN GREGORYONA
  Green Building Rough   05/04/2021   Partial Inspection   EDWIN GREGORYONA
  Reinforced Masonry Frame   05/04/2021   Partial Approval   EDWIN GREGORYONA
  Verify Sprinkler Sign Off   05/04/2021   Partial Inspection   EDWIN GREGORYONA
  Deputy Steel/Welding   05/05/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   05/06/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   05/07/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   05/10/2021   Partial Approval   EDWIN GREGORYONA
  Green Building Rough   05/10/2021   Partial Inspection   EDWIN GREGORYONA
  Reinforced Masonry Frame   05/10/2021   Partial Approval   EDWIN GREGORYONA
  Verify Sprinkler Sign Off   05/10/2021   Partial Inspection   EDWIN GREGORYONA
  Deputy Reinf. Concrete   05/11/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   05/12/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   05/13/2021   Partial Approval   EDWIN GREGORYONA
  Masonry Wall/Backfill   05/13/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   05/14/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Reinf. Concrete   05/17/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   05/17/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   05/18/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Reinf. Concrete   05/19/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   05/19/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   05/20/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   05/21/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   05/24/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   05/25/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Reinf. Concrete   05/26/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   05/26/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   05/27/2021   Partial Approval   EDWIN GREGORYONA
  Footing/Foundation/Slab   05/27/2021   Partial Approval   EDWIN GREGORYONA
  Green Building Rough   05/27/2021   Partial Inspection   EDWIN GREGORYONA
  Verify Sprinkler Sign Off   05/27/2021   Approved   EDWIN GREGORYONA
  Deputy Reinf. Concrete   05/28/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   05/28/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Shotcrete   06/16/2021   Partial Approval   EDWIN GREGORYONA
  Green Building Rough   06/16/2021   Partial Inspection   EDWIN GREGORYONA
  Reinforced Concrete Frame   06/16/2021   Partial Approval   EDWIN GREGORYONA
  Green Building Rough   06/24/2021   Not Ready for Inspection   EDWIN GREGORYONA
  Reinforced Concrete Frame   06/24/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Reinf. Concrete   06/25/2021   Partial Approval   EDWIN GREGORYONA
  Footing/Foundation/Slab   06/29/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   07/09/2021   Conditional Approval   JONATHAN QUACH
  Reinforced Concrete Frame   07/16/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Reinf. Concrete   07/19/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   07/19/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   07/20/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   07/21/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   07/22/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   07/23/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Reinf. Concrete   07/30/2021   Conditional Approval   TIMOTHY BUXTON
  Footing/Foundation/Slab   08/04/2021   Partial Approval   EDWIN GREGORYONA
  Reinforced Concrete Frame   08/10/2021   Partial Approval   EDWIN GREGORYONA
  Green Building Rough   08/12/2021   Partial Inspection   EDWIN GREGORYONA
  Masonry Wall/Backfill   08/12/2021   Partial Approval   EDWIN GREGORYONA
  Reinforced Concrete Frame   08/16/2021   Partial Approval   EDWIN GREGORYONA
  Reinforced Concrete Frame   08/26/2021   Order to Comply Issued   EDWIN GREGORYONA
  Deputy Steel/Welding   08/31/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   09/01/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Grading   09/02/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   09/02/2021   Partial Approval   EDWIN GREGORYONA
  Reinforced Concrete Frame   09/02/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Grading   09/03/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   09/03/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   09/07/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   09/14/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   09/15/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   09/16/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   09/17/2021   Conditional Approval   MARK FERRARI
  Deputy Grading   09/20/2021   Conditional Approval   MARK FERRARI
  Deputy Steel/Welding   09/20/2021   Conditional Approval   JONATHAN QUACH
  Deputy Steel/Welding   09/23/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   09/24/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   09/27/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   09/28/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   09/29/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   09/30/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   10/01/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   10/04/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   10/05/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   10/07/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   10/08/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   10/12/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   10/13/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   10/14/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   10/22/2021   Conditional Approval   DANIEL COLLINS
  Deputy Steel/Welding   10/25/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   10/26/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   10/27/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   10/28/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   11/12/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   11/15/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   11/16/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   11/17/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   11/18/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   11/19/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   11/22/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   11/23/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Drilled-In Anchors   12/20/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Fireproofing   12/20/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Reinf. Concrete   12/20/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Drilled-In Anchors   12/21/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Fireproofing   12/21/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Reinf. Concrete   12/21/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Drilled-In Anchors   12/22/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Fireproofing   12/22/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Reinf. Concrete   12/22/2021   Partial Approval   EDWIN GREGORYONA
  Deputy Drilled-In Anchors   12/23/2021   Conditional Approval   DAVID BURKHEAD
  Deputy Fireproofing   12/23/2021   Conditional Approval   DAVID BURKHEAD
  Deputy Reinf. Concrete   12/23/2021   Conditional Approval   DAVID BURKHEAD
  Reinforced Concrete Frame   02/08/2022   Partial Approval   EDWIN GREGORYONA
  Deputy Grading   02/10/2022   Partial Approval   EDWIN GREGORYONA
  Deputy Grading   02/11/2022   Partial Approval   EDWIN GREGORYONA
  Deputy Grading   02/14/2022   Partial Approval   EDWIN GREGORYONA
  Deputy Grading   02/15/2022   Partial Approval   EDWIN GREGORYONA
  Deputy Grading   02/16/2022   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   03/23/2022   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   03/24/2022   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   03/25/2022   Partial Approval   EDWIN GREGORYONA
  Reinforced Concrete Frame   04/07/2022   Partial Approval   EDWIN GREGORYONA
  Reinforced Concrete Frame   04/13/2022   Partial Approval   EDWIN GREGORYONA
  Masonry Wall/Backfill   04/25/2022   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   04/27/2022   Conditional Approval   DAVID BURKHEAD
  Deputy Steel/Welding   04/28/2022   Partial Approval   EDWIN GREGORYONA
  Green Building Rough   04/28/2022   Approved   EDWIN GREGORYONA
  Reinforced Masonry Frame   04/28/2022   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   04/29/2022   Partial Approval   EDWIN GREGORYONA
  Light Gage Steel Frame   05/02/2022   Partial Inspection   EDWIN GREGORYONA
  Light Gage Steel Frame   05/11/2022   Partial Approval   EDWIN GREGORYONA
  Reinforced Concrete Frame   05/23/2022   Partial Approval   EDWIN GREGORYONA
  Footing/Foundation/Slab   07/20/2022   Partial Approval   EDWIN GREGORYONA
  Reinforced Concrete Frame   08/02/2022   Partial Approval   JAMES POWERS
  Reinforced Concrete Frame   08/11/2022   Partial Approval   EDWIN GREGORYONA
  Reinforced Concrete Frame   08/19/2022   Partial Approval   EDWIN GREGORYONA
  Reinforced Concrete Frame   08/26/2022   Partial Inspection   EDWIN GREGORYONA
  Reinforced Concrete Frame   09/13/2022   Partial Approval   EDWIN GREGORYONA
  Reinforced Concrete Frame   09/19/2022   Partial Approval   EDWIN GREGORYONA
  Reinforced Concrete Frame   09/27/2022   Partial Approval   EDWIN GREGORYONA
  Reinforced Concrete Frame   09/30/2022   Partial Approval   EDWIN GREGORYONA
  Reinforced Concrete Frame   10/28/2022   Partial Approval   EDWIN GREGORYONA
  Pre-Inspection   11/09/2022   Approved   EDWIN GREGORYONA
  Footing/Foundation/Slab   12/05/2022   Partial Approval   EDWIN GREGORYONA
  Drywall Nailing   12/09/2022   Not Ready for Inspection   EDWIN GREGORYONA
  Final   12/09/2022   Partial Inspection   EDWIN GREGORYONA
  Footing/Foundation/Slab   12/09/2022   Not Ready for Inspection   EDWIN GREGORYONA
  Green Building Final   12/09/2022   Not Ready for Inspection   EDWIN GREGORYONA
  Reinforced Masonry Frame   12/09/2022   Not Ready for Inspection   EDWIN GREGORYONA
  SGSOV-Seismic Gas S/O Valve   12/09/2022   SGSOV Approved   EDWIN GREGORYONA
  Smoke Detectors   12/09/2022   Approved   EDWIN GREGORYONA
  Structural Steel Frame   12/09/2022   Not Ready for Inspection   EDWIN GREGORYONA
  Drywall Nailing   01/13/2023   Approved   EDWIN GREGORYONA
  Final   01/13/2023   Not Ready for Inspection   EDWIN GREGORYONA
  Footing/Foundation/Slab   01/13/2023   Approved   EDWIN GREGORYONA
  Green Building Final   01/13/2023   Not Ready for Inspection   EDWIN GREGORYONA
  Reinforced Masonry Frame   01/13/2023   Not Ready for Inspection   EDWIN GREGORYONA
  Structural Steel Frame   01/13/2023   Approved   EDWIN GREGORYONA
  Special/Order Compliance   07/06/2023   Approved   EDWIN GREGORYONA
  Final   12/19/2023   OK to Issue CofO   EDWIN GREGORYONA
  Green Building Final   12/19/2023   Approved   EDWIN GREGORYONA
  Reinforced Masonry Frame   12/19/2023   Approved   EDWIN GREGORYONA

BACK     NEW SEARCH