889 S FRANCISCO ST 90017
APPLICATION / PERMIT NUMBER: 13010-10000-03024
PLAN CHECK / JOB NUMBER: B13LA12211

Plan Check and Permit Information


GROUP: Building
TYPE: Bldg-New
SUB-TYPE: Commercial
PRIMARY USE: (5) Apartment
WORK DESCRIPTION: Core and Shell only for a new 39 story residential building, including 308 residences on 32 floors, a 7-story podium with an assessory pool/amenity deck and 6 levels of above-grade parking, 2 levels of below grade parking, and rooftop mechanical areas
PERMIT ISSUED: Yes PERMIT ISSUE DATE: 02/25/2015 ISSUING OFFICE: Metro
CURRENT STATUS: CofO Corrected CURRENT STATUS DATE: 05/09/2018

Permit Application Status History
Submitted 11/15/2013 APPLICANT
Assigned to Plan Check Engineer 11/21/2013 ALLEN MANALANSAN
Corrections Issued 12/03/2013 ALLEN MANALANSAN
Disabled Access Plans Picked Up 12/03/2013 APPLICANT
Quality Review Completed 12/04/2013 CHARLES CHANG
Building Plans Picked Up 12/04/2013 APPLICANT
Applicant returned to address corrections 04/22/2014 ALLEN MANALANSAN
Applicant returned to address corrections 04/30/2014 ALLEN MANALANSAN
Applicant returned to address corrections 05/21/2014 CHARLES CHANG
Applicant returned to address corrections 05/29/2014 CHARLES CHANG
Applicant returned to address corrections 06/10/2014 SAI KHUM
Applicant returned to address corrections 06/23/2014 ALLEN MANALANSAN
Applicant returned to address corrections 07/02/2014 ALLEN MANALANSAN
Applicant returned to address corrections 07/03/2014 SUEN LIEU
Applicant returned to address corrections 07/10/2014 CHARLES CHANG
Applicant returned to address corrections 07/15/2014 ALLEN MANALANSAN
Applicant returned to address corrections 07/22/2014 ALLEN MANALANSAN
Applicant returned to address corrections 09/09/2014 ALLEN MANALANSAN
Applicant returned to address corrections 09/24/2014 ALLEN MANALANSAN
Applicant returned to address corrections 01/22/2015 SAI KHUM
Applicant returned to address corrections 02/04/2015 ALLEN MANALANSAN
Applicant returned to address corrections 02/04/2015 SAI KHUM
Applicant returned to address corrections 02/12/2015 SAI KHUM
Applicant returned to address corrections 02/13/2015 SAI KHUM
Plan Check Approved 02/18/2015 SAI KWAN KHUM
Issued 02/25/2015 LADBS
CofO in Progress 03/27/2018 LESLIE TRUJILLO
CofO Issued-Status Void 03/28/2018 RICKEY JACKSON
Permit Finaled-Status Void 03/28/2018 RICKEY JACKSON
Re-Activate Permit 04/10/2018 RICKEY JACKSON
CofO Corrected-Status Void 04/10/2018 RICKEY JACKSON
Permit Finaled-Status Void 04/10/2018 RICKEY JACKSON
Re-Activate Permit 04/30/2018 RICKEY JACKSON
Permit Finaled 05/09/2018 RICKEY JACKSON
CofO Corrected 05/09/2018 RICKEY JACKSON
Permit Finaled 05/09/2018 RICKEY JACKSON

Permit Application Clearance Information
Address approval Cleared 12/23/2013 ARMENIA HERNANDEZ
Hydrant and Access approval Cleared 01/16/2014 JOHN DALLAS
Construction within easement Cleared 01/29/2014 WALTER RAMIREZ
DAS Clearance Cleared 02/05/2014 WAI LAU
Work Adjacent to Public Way Cleared 08/14/2014 ARMENIA HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 12/22/2014 JOSHUA LOPEZ
Highway dedication Cleared 12/29/2014 ARMENIA HERNANDEZ
Driveway location Cleared 01/23/2015 TAIMOUR TANAVOLI
Internal circulation Cleared 01/23/2015 TAIMOUR TANAVOLI
Sewer availability Cleared 01/29/2015 KARAN PATEL
Low Impact Development Cleared 02/10/2015 AMMAR ELTAWIL
Stormwater Pollution Mitigatn Cleared 02/10/2015 AMMAR ELTAWIL
Excavation more than 5-ft deep Cleared 02/11/2015 CALOSHA APPROVED
Project located in CRA area Cleared 02/11/2015 JIM URQUHART
Green Code Cleared 02/12/2015 RUSSELL KELLY
"D" conditions Cleared 02/13/2015 MARITZA PRZEKOP
"T" removal Cleared 02/13/2015 MARITZA PRZEKOP
Building over 3-story or 36-ft Cleared 02/13/2015 CALOSHA APPROVED
CPC Cleared 02/13/2015 MARITZA PRZEKOP
DAS Clearance Cleared 02/13/2015 WAI LAU
Frnt yard landscape/Water mgmt Cleared 02/13/2015 MARITZA PRZEKOP
Miscellaneous Cleared 02/13/2015 MARITZA PRZEKOP
Opn space landscape/Water mgmt Cleared 02/13/2015 MARITZA PRZEKOP
Permit Cleared 02/13/2015 WESLEY TANIJIRI
Roof/Waste drainage to street Cleared 02/13/2015 WESLEY TANIJIRI
Site Plan review Cleared 02/13/2015 MARITZA PRZEKOP
Tract Map conditions Cleared 02/13/2015 MARITZA PRZEKOP
ZA Case Cleared 02/13/2015 MARITZA PRZEKOP
ZI Cleared 02/13/2015 MARITZA PRZEKOP
Title 19 building approval Cleared 02/17/2015 HANI MALKI

Licensed Professional/Contractor Information
Architect Information
Cohen, Andrew Phillip; Lic. No.: C12855
500 S FIGUEROA STREET
LOS ANGELES, CA  90071
Architect Information
Wicksman, Warwick Ian; Lic. No.: C23350
22844 DOLOROSA ST
WOODLAND HILLS, CA  91367
Contractor Information
Webcor Construction L P; Lic. No.: 899242-A
1751 HARBOR BAY PARKWAY #200
ALAMEDA, CA  94502
Engineer Information
Davis, Richard Hays; Lic. No.: C48082
2015 CANTATA DR
LOS ANGELES, CA  90068
Engineer Information
Islam, Mohammed Saiful; Lic. No.: S4083
155 N LAKE AVE SUITE 600
PASADENA, CA  91101
Engineer Information
Tatusian, Sarkis Vortik; Lic. No.: GE2118
24 VISTA DEL SOL
LAGUNA BEACH, CA  92651
Engineer Information
Wahl, Douglas Aaron James; Lic. No.: C74422
10381 MEADS AVE UNIT G
ORANGE, CA  92869
Landscape Architect Information
Packer, Jennifer Leigh; Lic. No.: LA4933
27206 SYCAMORE MEADOW DRIVE
VALENCIA, CA  91381

Inspection Activity Information

Inspector Information
NICK DANERI, (213) 202-5615
Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspection Request(s)
  No data available

Inspection Request History
  Floor/Roof Diaphrgm/Shear Wall   03/02/2015   Order to Comply Issued   WILLIAM THOMPSON
  Footing/Foundation/Slab   03/04/2015   Partial Approval   WILLIAM THOMPSON
  SWPPP-Const. Storm Water   03/04/2015   Completed   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   03/13/2015   Partial Approval   WILLIAM THOMPSON
  Deputy Reinf. Concrete   03/16/2015   Approved   WILLIAM THOMPSON
  Deputy Reinf. Concrete   03/17/2015   Conditional Approval   WILLIAM THOMPSON
  Deputy Reinf. Concrete   03/18/2015   Approved   WILLIAM THOMPSON
  Deputy Reinf. Concrete   03/19/2015   Approved   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   03/19/2015   Partial Approval   WILLIAM THOMPSON
  Deputy Reinf. Concrete   03/20/2015   Approved   WILLIAM THOMPSON
  Footing/Foundation/Slab   03/20/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   03/23/2015   Partial Approval   WILLIAM THOMPSON
  Footing/Foundation/Slab   03/31/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   04/10/2015   Partial Approval   WILLIAM THOMPSON
  Excavation/Setback/Form/Re-Bar   04/14/2015   Partial Inspection   WILLIAM THOMPSON
  Footing/Foundation/Slab   04/20/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   04/23/2015   Partial Inspection   WILLIAM THOMPSON
  Footing/Foundation/Slab   04/27/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   04/29/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   05/04/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   05/06/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   05/07/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   05/11/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   05/13/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   05/15/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   05/26/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   05/27/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   05/29/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   06/01/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   06/03/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   06/04/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   06/05/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   06/08/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   06/09/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   06/18/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   06/19/2015   Partial Approval   LESLIE TRUJILLO
  Floor/Roof Diaphrgm/Shear Wall   06/22/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   06/24/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   06/25/2015   Partial Approval   WILLIAM THOMPSON
  Masonry Wall/Backfill   06/26/2015   Partial Approval   WILLIAM THOMPSON
  Footing/Foundation/Slab   06/29/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   06/30/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   07/06/2015   Partial Approval   WILLIAM THOMPSON
  Masonry Wall/Backfill   07/06/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   07/07/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   07/08/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   07/14/2015   Partial Approval   WILLIAM THOMPSON
  Masonry Wall/Backfill   07/16/2015   Partial Approval   WILLIAM THOMPSON
  Excavation/Setback/Form/Re-Bar   07/20/2015   Partial Approval   WILLIAM THOMPSON
  Masonry Wall/Backfill   07/20/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   07/23/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   07/27/2015   Partial Approval   WILLIAM THOMPSON
  Masonry Wall/Backfill   07/27/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   07/28/2015   Partial Approval   WILLIAM THOMPSON
  Light Gage Steel Frame   07/28/2015   Partial Approval   WILLIAM THOMPSON
  Masonry Wall/Backfill   07/28/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   07/29/2015   Partial Approval   WILLIAM THOMPSON
  Light Gage Steel Frame   07/29/2015   Partial Approval   WILLIAM THOMPSON
  Masonry Wall/Backfill   07/29/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   07/31/2015   Partial Approval   WILLIAM THOMPSON
  Masonry Wall/Backfill   07/31/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   08/03/2015   Partial Approval   WILLIAM THOMPSON
  Light Gage Steel Frame   08/03/2015   Partial Approval   WILLIAM THOMPSON
  Masonry Wall/Backfill   08/03/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   08/04/2015   Partial Approval   WILLIAM THOMPSON
  Light Gage Steel Frame   08/04/2015   Partial Approval   WILLIAM THOMPSON
  Masonry Wall/Backfill   08/04/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   08/05/2015   Partial Approval   WILLIAM THOMPSON
  Light Gage Steel Frame   08/05/2015   Partial Approval   WILLIAM THOMPSON
  Masonry Wall/Backfill   08/05/2015   Partial Approval   WILLIAM THOMPSON
  Light Gage Steel Frame   08/06/2015   Partial Approval   WILLIAM THOMPSON
  Masonry Wall/Backfill   08/06/2015   Partial Approval   WILLIAM THOMPSON
  Structural Steel Frame   08/06/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   08/10/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   08/11/2015   Partial Approval   WILLIAM THOMPSON
  Masonry Wall/Backfill   08/11/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   08/13/2015   Partial Approval   WILLIAM THOMPSON
  Light Gage Steel Frame   08/13/2015   Partial Approval   WILLIAM THOMPSON
  Masonry Wall/Backfill   08/13/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   08/17/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   08/19/2015   Partial Approval   WILLIAM THOMPSON
  Footing/Foundation/Slab   08/19/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   08/21/2015   Partial Approval   WILLIAM THOMPSON
  Light Gage Steel Frame   08/21/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   08/24/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   08/25/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   08/26/2015   Partial Approval   WILLIAM THOMPSON
  Light Gage Steel Frame   08/26/2015   Partial Approval   WILLIAM THOMPSON
  Masonry Wall/Backfill   08/26/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   08/27/2015   Partial Approval   WILLIAM THOMPSON
  Light Gage Steel Frame   08/27/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   08/28/2015   Partial Approval   WILLIAM THOMPSON
  Light Gage Steel Frame   08/28/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   09/02/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   09/03/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   09/08/2015   Partial Approval   WILLIAM THOMPSON
  Light Gage Steel Frame   09/08/2015   Partial Approval   WILLIAM THOMPSON
  Masonry Wall/Backfill   09/08/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   09/09/2015   Partial Approval   WILLIAM THOMPSON
  Drywall Nailing   09/14/2015   Partial Inspection   JAMES POWERS
  Light Gage Steel Frame   09/14/2015   Not Ready for Inspection   JAMES POWERS
  Light Gage Steel Frame   09/15/2015   Not Ready for Inspection   JAMES POWERS
  Light Gage Steel Frame   09/16/2015   Not Ready for Inspection   JAMES POWERS
  Light Gage Steel Frame   09/18/2015   Partial Approval   JAMES POWERS
  Reinforced Concrete Frame   09/21/2015   Partial Approval   JAMES POWERS
  Verify Sprinkler Sign Off   09/21/2015   Not Ready for Inspection   JAMES POWERS
  Light Gage Steel Frame   09/24/2015   Partial Approval   JAMES POWERS
  Light Gage Steel Frame   09/29/2015   Partial Approval   WILLIAM THOMPSON
  Reinforced Concrete Frame   09/29/2015   Partial Approval   WILLIAM THOMPSON
  Verify Sprinkler Sign Off   09/29/2015   Not Ready for Inspection   WILLIAM THOMPSON
  Light Gage Steel Frame   09/30/2015   Partial Approval   WILLIAM THOMPSON
  Drywall Nailing   10/01/2015   Partial Approval   WILLIAM THOMPSON
  Green Building Rough   10/01/2015   Not Ready for Inspection   JOHN KLARIN
  Drywall Nailing   10/08/2015   Partial Approval   WILLIAM THOMPSON
  SWPPP-Const. Storm Water   10/08/2015   Completed   WILLIAM THOMPSON
  Excavation/Setback/Form/Re-Bar   10/14/2015   Partial Approval   WILLIAM THOMPSON
  Light Gage Steel Frame   10/14/2015   Partial Approval   WILLIAM THOMPSON
  Drywall Nailing   10/15/2015   Partial Approval   WILLIAM THOMPSON
  Excavation/Setback/Form/Re-Bar   10/16/2015   Partial Approval   WILLIAM THOMPSON
  Light Gage Steel Frame   10/16/2015   Partial Approval   WILLIAM THOMPSON
  Excavation/Setback/Form/Re-Bar   10/20/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   10/21/2015   Partial Approval   WILLIAM THOMPSON
  Structural Steel Frame   10/21/2015   Partial Approval   WILLIAM THOMPSON
  Insulation   10/22/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   10/23/2015   Partial Approval   WILLIAM THOMPSON
  Reinforced Concrete Frame   10/27/2015   Partial Approval   WILLIAM THOMPSON
  Verify Sprinkler Sign Off   10/27/2015   Partial Approval   WILLIAM THOMPSON
  Light Gage Steel Frame   10/28/2015   Partial Approval   WILLIAM THOMPSON
  Light Gage Steel Frame   11/03/2015   Partial Approval   WILLIAM THOMPSON
  Reinforced Concrete Frame   11/04/2015   Partial Approval   WILLIAM THOMPSON
  Verify Sprinkler Sign Off   11/04/2015   Partial Approval   WILLIAM THOMPSON
  Light Gage Steel Frame   11/05/2015   Partial Approval   WILLIAM THOMPSON
  Reinforced Concrete Frame   11/13/2015   Partial Approval   WILLIAM THOMPSON
  Verify Sprinkler Sign Off   11/13/2015   Partial Approval   WILLIAM THOMPSON
  Excavation/Setback/Form/Re-Bar   11/16/2015   Partial Approval   WILLIAM THOMPSON
  Insulation   11/16/2015   Partial Approval   WILLIAM THOMPSON
  Excavation/Setback/Form/Re-Bar   11/17/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   11/17/2015   Partial Approval   WILLIAM THOMPSON
  Excavation/Setback/Form/Re-Bar   11/18/2015   Partial Approval   WILLIAM THOMPSON
  Light Gage Steel Frame   11/20/2015   Partial Approval   WILLIAM THOMPSON
  Structural Steel Frame   11/20/2015   Partial Approval   WILLIAM THOMPSON
  Excavation/Setback/Form/Re-Bar   11/24/2015   Partial Approval   WILLIAM THOMPSON
  Floor/Roof Diaphrgm/Shear Wall   12/02/2015   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   12/07/2015   Partial Approval   SAKO AGHAZARIAN
  Floor/Roof Diaphrgm/Shear Wall   12/08/2015   Partial Approval   SAKO AGHAZARIAN
  Insulation   12/08/2015   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   12/08/2015   Partial Approval   SAKO AGHAZARIAN
  Excavation/Setback/Form/Re-Bar   12/15/2015   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   12/15/2015   Partial Inspection   SAKO AGHAZARIAN
  Drywall Nailing   12/17/2015   Partial Approval   SAKO AGHAZARIAN
  Insulation   12/17/2015   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   12/17/2015   Partial Approval   SAKO AGHAZARIAN
  Floor/Roof Diaphrgm/Shear Wall   12/23/2015   Partial Approval   SAKO AGHAZARIAN
  Green Building Rough   12/23/2015   Partial Approval   DONALD CRICHLOW
  Pre-Inspection   12/23/2015   Approved   SAKO AGHAZARIAN
  Masonry Wall/Backfill   01/04/2016   Partial Inspection   SAKO AGHAZARIAN
  Light Gage Steel Frame   01/05/2016   Partial Approval   SAKO AGHAZARIAN
  Insulation   01/11/2016   Partial Inspection   SAKO AGHAZARIAN
  Light Gage Steel Frame   01/11/2016   Partial Inspection   SAKO AGHAZARIAN
  Insulation   01/15/2016   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   01/15/2016   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   01/19/2016   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   01/20/2016   Partial Approval   SAKO AGHAZARIAN
  Insulation   01/27/2016   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   01/27/2016   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   02/02/2016   Partial Approval   SAKO AGHAZARIAN
  Green Building Rough   02/03/2016   Partial Approval   DONALD CRICHLOW
  Light Gage Steel Frame   02/05/2016   Partial Approval   SAKO AGHAZARIAN
  Drywall Nailing   02/10/2016   Partial Approval   SAKO AGHAZARIAN
  Green Building Rough   02/10/2016   Partial Approval   DONALD CRICHLOW
  Insulation   02/10/2016   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   02/10/2016   Partial Approval   SAKO AGHAZARIAN
  Insulation   02/11/2016   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   02/11/2016   Partial Approval   SAKO AGHAZARIAN
  Insulation   02/17/2016   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   02/17/2016   Partial Approval   SAKO AGHAZARIAN
  Insulation   02/23/2016   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   02/23/2016   Partial Approval   SAKO AGHAZARIAN
  Insulation   02/26/2016   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   02/26/2016   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   02/29/2016   Partial Approval   SAKO AGHAZARIAN
  Insulation   03/03/2016   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   03/03/2016   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   03/08/2016   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   03/16/2016   Partial Approval   SAKO AGHAZARIAN
  Insulation   03/24/2016   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   03/24/2016   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   04/06/2016   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   04/07/2016   Partial Approval   SAKO AGHAZARIAN
  Insulation   04/12/2016   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   04/12/2016   Partial Approval   SAKO AGHAZARIAN
  Footing/Foundation/Slab   04/15/2016   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   04/15/2016   Partial Inspection   SAKO AGHAZARIAN
  Insulation   04/25/2016   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   04/25/2016   Partial Approval   SAKO AGHAZARIAN
  Footing/Foundation/Slab   04/26/2016   Partial Approval   SAKO AGHAZARIAN
  Footing/Foundation/Slab   04/29/2016   Partial Inspection   SAKO AGHAZARIAN
  Drywall Nailing   05/02/2016   Partial Approval   SAKO AGHAZARIAN
  Green Building Rough   05/02/2016   Not Ready for Inspection   DONALD CRICHLOW
  Light Gage Steel Frame   05/02/2016   Partial Approval   SAKO AGHAZARIAN
  Footing/Foundation/Slab   05/04/2016   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   05/04/2016   Partial Approval   SAKO AGHAZARIAN
  Excavation/Setback/Form/Re-Bar   05/06/2016   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   05/06/2016   Partial Approval   SAKO AGHAZARIAN
  Excavation/Setback/Form/Re-Bar   05/11/2016   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   05/11/2016   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   06/02/2016   Partial Approval   SAKO AGHAZARIAN
  Excavation/Setback/Form/Re-Bar   06/09/2016   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   06/09/2016   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   06/21/2016   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   06/23/2016   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   07/11/2016   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   07/25/2016   Partial Approval   GREGORY POMISH
  Drywall Nailing   07/28/2016   Partial Inspection   SAKO AGHAZARIAN
  Green Building Rough   07/28/2016   Not Ready for Inspection   DAVID MATSON
  Light Gage Steel Frame   07/28/2016   Partial Inspection   SAKO AGHAZARIAN
  Light Gage Steel Frame   08/01/2016   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   08/11/2016   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   08/16/2016   Partial Inspection   SAKO AGHAZARIAN
  Light Gage Steel Frame   08/30/2016   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   09/09/2016   Not Ready for Inspection   LESLIE TRUJILLO
  Reinforced Masonry Frame   09/09/2016   Not Ready for Inspection   LESLIE TRUJILLO
  Light Gage Steel Frame   09/12/2016   Partial Inspection   SAKO AGHAZARIAN
  Light Gage Steel Frame   09/13/2016   Partial Inspection   SAKO AGHAZARIAN
  Light Gage Steel Frame   10/13/2016   Partial Inspection   SAKO AGHAZARIAN
  Interior/Exterior Lathing   10/26/2016   Partial Approval   SAKO AGHAZARIAN
  Light Gage Steel Frame   10/27/2016   Partial Inspection   SAKO AGHAZARIAN
  Wall Anchors   10/27/2016   Approved   SAKO AGHAZARIAN
  Light Gage Steel Frame   10/31/2016   Partial Approval   SAKO AGHAZARIAN
  Footing/Foundation/Slab   11/18/2016   Partial Approval   SAKO AGHAZARIAN
  SWPPP-Const. Storm Water   11/18/2016   Completed   SAKO AGHAZARIAN
  Light Gage Steel Frame   11/21/2016   Approved   SAKO AGHAZARIAN
  Pre-Inspection   12/01/2016   Approved   SAKO AGHAZARIAN
  Grading Pre-Inspection   12/05/2016   Approved   SAKO AGHAZARIAN
  Pre-Inspection   12/06/2016   Approved   SAKO AGHAZARIAN
  Pre-Inspection   12/08/2016   Approved   SAKO AGHAZARIAN
  SUSMP-Std. Urban Storm Water   12/09/2016   Approved   SAKO AGHAZARIAN
  Green Building Final   12/15/2016   Partial Inspection   DONALD CRICHLOW
  Green Building Rough   12/15/2016   Partial Approval   DONALD CRICHLOW
  Pre-Inspection   12/19/2016   Approved   SAKO AGHAZARIAN
  Drywall Nailing   12/27/2016   Partial Approval   SAKO AGHAZARIAN
  Final   12/27/2016   Partial Inspection   SAKO AGHAZARIAN
  Footing/Foundation/Slab   12/27/2016   Approved   SAKO AGHAZARIAN
  Green Building Final   12/27/2016   Partial Approval   DONALD CRICHLOW
  Green Building Rough   12/27/2016   Approved   DONALD CRICHLOW
  Pre-Inspection   12/27/2016   Approved   SAKO AGHAZARIAN
  Reinforced Concrete Frame   12/27/2016   Approved   SAKO AGHAZARIAN
  SGSOV-Seismic Gas S/O Valve   12/27/2016   SGSOV Approved   SAKO AGHAZARIAN
  Smoke Detectors   12/27/2016   Approved   SAKO AGHAZARIAN
  Verify Sprinkler Sign Off   12/27/2016   Approved   SAKO AGHAZARIAN
  Final   12/30/2016   Partial Inspection   SAKO AGHAZARIAN
  Pre-Inspection   02/01/2017   Approved   SAKO AGHAZARIAN
  Insulation   03/09/2017   Partial Approval   SAKO AGHAZARIAN
  Drywall Nailing   03/10/2017   Approved   SAKO AGHAZARIAN
  Final   03/10/2017   Partial Inspection   SAKO AGHAZARIAN
  Green Building Final   03/10/2017   Not Ready for Inspection   JOHN KLARIN
  Final   03/14/2017   Partial Inspection   SAKO AGHAZARIAN
  Special/Order Compliance   03/15/2017   Approved   SAKO AGHAZARIAN
  Final   05/26/2017   Partial Inspection   SAKO AGHAZARIAN
  Green Building Final   05/26/2017   No Access for Inspection   RICHARD DOCKUS
  Final   06/02/2017   Partial Inspection   SAKO AGHAZARIAN
  Green Building Final   06/02/2017   Not Ready for Inspection   DONALD CRICHLOW
  Special/Order Compliance   06/28/2017   Approved   SAKO AGHAZARIAN
  Final   10/31/2017   Partial Inspection   SAKO AGHAZARIAN
  Green Building Final   10/31/2017   Partial Inspection   RICHARD DOCKUS
  SWPPP-Const. Storm Water   10/31/2017   Completed   SAKO AGHAZARIAN
  Special/Order Compliance   12/05/2017   Approved   SAKO AGHAZARIAN
  Green Building Final   12/08/2017   Not Ready for Inspection   JEFF BYTHEWAY
  Final   03/15/2018   Not Ready for Inspection   LESLIE TRUJILLO
  Green Building Final   03/15/2018   Approved   LESLIE TRUJILLO
  Final   03/23/2018   Not Ready for Inspection   LESLIE TRUJILLO
  Final   03/27/2018   OK to Issue CofO   LESLIE TRUJILLO