Submitted |
03/11/2015 |
APPLICANT |
Assigned to Plan Check Engineer |
03/25/2015 |
STEVEN KIM |
Plans on Hold |
03/25/2015 |
BINH PHAN |
Disabled Access Plans Picked Up |
04/03/2015 |
APPLICANT |
Hold Released |
04/08/2015 |
BINH PHAN |
Green Plans Picked Up |
04/10/2015 |
APPLICANT |
Corrections Issued |
05/19/2015 |
STEVEN KIM |
Quality Review Completed |
05/19/2015 |
TIEN JEN WANG |
Applicant returned to address corrections |
08/11/2015 |
STEVEN KIM |
Applicant returned to address corrections |
09/08/2015 |
STEVEN KIM |
Applicant returned to address corrections |
09/11/2015 |
STEVEN KIM |
Applicant returned to address corrections |
09/23/2015 |
STEVEN KIM |
Applicant returned to address corrections |
09/25/2015 |
STEVEN KIM |
Applicant returned to address corrections |
09/29/2015 |
STEVEN KIM |
Applicant returned to address corrections |
10/19/2015 |
STEVEN KIM |
Applicant returned to address corrections |
10/20/2015 |
STEVEN KIM |
Applicant returned to address corrections |
10/21/2015 |
STEVEN KIM |
Applicant returned to address corrections |
10/27/2015 |
STEVEN KIM |
Applicant returned to address corrections |
10/28/2015 |
STEVEN KIM |
Plan Check Approved |
02/02/2016 |
STEVEN KIM |
Issued |
02/02/2016 |
LADBS |
CofO in Progress |
04/17/2019 |
JEFF BYTHEWAY |
CofO Issued-Status Void |
04/21/2019 |
DAVID TSAU |
Permit Finaled-Status Void |
04/21/2019 |
DAVID TSAU |
Re-Activate Permit |
05/08/2019 |
DAVID TSAU |
Re-Activate Permit |
06/03/2019 |
DAVID TSAU |
CofO Corrected-Status Void |
06/03/2019 |
DAVID TSAU |
Permit Finaled-Status Void |
06/03/2019 |
DAVID TSAU |
CofO Corrected |
06/06/2019 |
DAVID TSAU |
Permit Finaled |
06/06/2019 |
DAVID TSAU |
Low Impact Development |
Cleared |
04/21/2015 |
MICHAEL SCADUTO |
Stormwater Pollution Mitigatn |
Cleared |
04/21/2015 |
MICHAEL SCADUTO |
Internal circulation |
Cleared |
05/18/2015 |
WESTON PRINGLE |
Hydrant and Access approval |
Cleared |
07/07/2015 |
ROBERT DUFF |
Sewer availability |
Cleared |
08/14/2015 |
KARAN PATEL |
Encroachment in public way |
Cleared |
08/24/2015 |
JAMES KHO |
Miscellaneous |
Cleared |
08/24/2015 |
JAMES KHO |
Eng Process Fee Ord 176,300 |
Cleared |
10/13/2015 |
KARAN PATEL |
Permit |
Cleared |
10/14/2015 |
DANIEL SUE |
Roof/Waste drainage to street |
Cleared |
10/14/2015 |
DANIEL SUE |
Highway dedication |
Cleared |
10/15/2015 |
JAMES KHO |
Work Adjacent to Public Way |
Cleared |
10/15/2015 |
DAVID PEREZ |
Building over 3-story or 36-ft |
Cleared |
10/20/2015 |
CALOSHA APPROVED |
Fire Marshall Fire Life Safety |
Cleared |
10/21/2015 |
ANDREW KO |
Green Code |
Cleared |
10/21/2015 |
MICHAEL AYERS |
Disturb/Remove Protected Trees |
Cleared |
10/22/2015 |
TROY CALLEROS |
DAS Clearance |
Cleared |
10/23/2015 |
WAI LAU |
Excavation more than 5-ft deep |
Cleared |
10/23/2015 |
CALOSHA APPROVED |
Metro Rail approval |
Cleared |
10/27/2015 |
THAN WIN |
Address approval |
Cleared |
11/19/2015 |
AVALYN KAMACHI |
City Hist. Cultural Monument |
Cleared |
01/25/2016 |
LAMBERT GIESSINGER |
Historic monument |
Cleared |
01/25/2016 |
LAMBERT GIESSINGER |
Project located in CRA area |
Cleared |
01/25/2016 |
JIM URQUHART |
"D" conditions |
Cleared |
01/26/2016 |
ANDY RODRIGUEZ |
"Q" conditions |
Cleared |
01/26/2016 |
ANDY RODRIGUEZ |
CPC |
Cleared |
01/26/2016 |
ANDY RODRIGUEZ |
Housing density bonus |
Cleared |
01/26/2016 |
MARITES CUNANAN |
Miscellaneous |
Cleared |
01/26/2016 |
ANDY RODRIGUEZ |
Opn space landscape/Water mgmt |
Cleared |
01/26/2016 |
ANDY RODRIGUEZ |
Site Plan review |
Cleared |
01/26/2016 |
ANDY RODRIGUEZ |
Tract Map conditions |
Cleared |
01/26/2016 |
ANDY RODRIGUEZ |
ZI |
Cleared |
01/26/2016 |
ANDY RODRIGUEZ |
Historical monument |
Cleared |
01/29/2016 |
JIM URQUHART |
"T" removal |
Cleared |
02/01/2016 |
ANDY RODRIGUEZ |