Los Angeles department of building safty logo Permit and Inspection Report banner
936 S BURNSIDE AVE 90036
APPLICATION / PERMIT NUMBER: 14010-20000-04186
PLAN CHECK / JOB NUMBER: B14VN15998

Plan Check and Permit Information


GROUP: Building
TYPE: Bldg-New
SUB-TYPE: 1 or 2 Family Dwelling
PRIMARY USE: (1) Dwelling - Single Family
WORK DESCRIPTION: (N) 2 STORY SFD W/ ATT GARAGE. SPRINKLERS NFPA13D
PERMIT ISSUED: Yes PERMIT ISSUE DATE: 03/02/2015 ISSUING OFFICE: Metro
CURRENT STATUS: CofO Issued CURRENT STATUS DATE: 06/03/2016

Permit Application Status History
Submitted 12/31/2014 APPLICANT
Green Plans Picked Up 01/14/2015 APPLICANT
Assigned to Plan Check Engineer 01/22/2015 HERNAN ARREOLA
Corrections Issued 01/28/2015 HERNAN ARREOLA
Quality Review Completed 01/30/2015 BINH PHAN
Applicant returned to address corrections 02/12/2015 HERNAN ARREOLA
Plan Check Approved 02/26/2015 HERNAN ARREOLA
Issued 03/02/2015 LADBS
CofO in Progress 04/30/2016 DAVID CHAN
Permit Finaled 06/03/2016 MARK CASEY
CofO Issued 06/03/2016 MARK CASEY
Permit Finaled 06/03/2016 MARK CASEY

Permit Application Clearance Information
Eng Process Fee Ord 176,300 Cleared 02/05/2015 SANDRA FIGUEROA
Green Code Cleared 02/05/2015 MICHAEL AYERS
Low Impact Development Cleared 02/05/2015 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 02/05/2015 SANDRA FIGUEROA
Sewer availability Cleared 02/05/2015 SANDRA FIGUEROA

Licensed Professional/Contractor Information
Contractor Information
Owner-Builder
  
Engineer Information
Lee, Sang Youck; Lic. No.: S3821
3531 BROOKHILL ST
GLENDALE, CA  91214

Inspection Activity Information

Inspector Information
RONNIE MINDANAO, (213) 202-3252
Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspection Request(s)
  No data available

Inspection Request History
  Footing/Foundation/Slab   04/01/2015   Approved   DAVID CHAN
  METHANE-Barrier   04/01/2015   Approved   DAVID CHAN
  METHANE-Subgrade   04/01/2015   Approved   DAVID CHAN
  Deputy Reinf. Concrete   04/02/2015   Partial Approval   MARK HATFIELD
  BUILDING-Rough-Frame   04/17/2015   Partial Approval   DAVID CHAN
  PLUMBING-Rough   04/17/2015   Partial Approval   DAVID CHAN
  Floor/Roof Diaphrgm/Shear Wall   04/22/2015   Approved   DAVID CHAN
  BUILDING-Rough-Frame   08/25/2015   Approved   MARK HATFIELD
  Green Building Rough   08/25/2015   Approved   MARK HATFIELD
  METHANE-Rough   08/25/2015   Partial Inspection   MARK HATFIELD
  Rough-Elec/Plmb/HVAC   08/25/2015   Approved   MARK HATFIELD
  Verify Sprinkler Sign Off   08/25/2015   Approved   MARK HATFIELD
  Insulation   09/15/2015   Approved   DAVID CHAN
  Interior/Exterior Lathing   09/15/2015   Approved   DAVID CHAN
  Drywall Nailing   10/07/2015   Approved   DAVID CHAN
  ELECTRICAL-Final   03/04/2016   Approved   DAVID CHAN
  HVAC-Final   03/04/2016   Approved   DAVID CHAN
  PLUMBING-Final   03/04/2016   Approved   DAVID CHAN
  SGSOV-Seismic Gas S/O Valve   04/21/2016   SGSOV Not Ready   DAVID CHAN
  Service/Power Release   04/21/2016   Approved   DAVID CHAN
  Final   04/27/2016   OK to Issue CofO   DAVID CHAN
  Green Building Final   04/27/2016   Approved   DAVID CHAN
  SGSOV-Seismic Gas S/O Valve   04/27/2016   SGSOV Approved   DAVID CHAN
  Smoke Detectors   04/27/2016   Approved   DAVID CHAN

BACK     NEW SEARCH