Submitted |
06/16/2014 |
APPLICANT |
Assigned to Plan Check Engineer |
06/19/2014 |
SAI KHUM |
Corrections Issued |
07/01/2014 |
SAI KHUM |
Quality Review Completed |
07/02/2014 |
CHARLES CHANG |
Building Plans Picked Up |
07/29/2014 |
APPLICANT |
Applicant returned to address corrections |
09/02/2014 |
ALLEN MANALANSAN |
Applicant returned to address corrections |
09/09/2014 |
ALLEN MANALANSAN |
Applicant returned to address corrections |
10/07/2014 |
ALLEN MANALANSAN |
Applicant returned to address corrections |
10/29/2014 |
ALLEN MANALANSAN |
Applicant returned to address corrections |
11/04/2014 |
ALLEN MANALANSAN |
Applicant returned to address corrections |
11/20/2014 |
ALLEN MANALANSAN |
Applicant returned to address corrections |
12/02/2014 |
ALLEN MANALANSAN |
Applicant returned to address corrections |
01/14/2015 |
SAI KHUM |
Applicant returned to address corrections |
01/27/2015 |
ALLEN MANALANSAN |
Applicant returned to address corrections |
01/29/2015 |
SAI KHUM |
Applicant returned to address corrections |
02/11/2015 |
SAI KHUM |
Applicant returned to address corrections |
02/11/2015 |
ALLEN MANALANSAN |
Applicant returned to address corrections |
03/18/2015 |
SAI KHUM |
Applicant returned to address corrections |
07/20/2015 |
ALLEN MANALANSAN |
Applicant returned to address corrections |
09/03/2015 |
SAI KHUM |
Applicant returned to address corrections |
09/10/2015 |
SAI KHUM |
Applicant returned to address corrections |
09/16/2015 |
SAI KHUM |
Plan Check Approved |
09/23/2015 |
ALLEN MANALANSAN |
Issued |
09/23/2015 |
LADBS |
CofO in Progress |
07/20/2017 |
LESLIE TRUJILLO |
Permit Finaled |
07/20/2017 |
HAMID PISHEHVAR |
CofO Issued |
07/20/2017 |
HAMID PISHEHVAR |
Permit Finaled |
07/20/2017 |
HAMID PISHEHVAR |
Driveway location |
Cleared |
07/22/2014 |
EILEEN HUNT |
Internal circulation |
Cleared |
07/22/2014 |
EILEEN HUNT |
Address approval |
Cleared |
02/10/2015 |
ARMENIA HERNANDEZ |
Encroachment in public way |
Cleared |
02/10/2015 |
ARMENIA HERNANDEZ |
Highway dedication |
Cleared |
02/10/2015 |
ARMENIA HERNANDEZ |
Permit |
Cleared |
02/10/2015 |
ARMENIA HERNANDEZ |
Low Impact Development |
Cleared |
03/11/2015 |
AYMAN JABBOURI |
Eng Process Fee Ord 176,300 |
Cleared |
07/15/2015 |
ARMENIA HERNANDEZ |
Roof/Waste drainage to street |
Cleared |
07/15/2015 |
ARMENIA HERNANDEZ |
Work Adjacent to Public Way |
Cleared |
07/15/2015 |
ARMENIA HERNANDEZ |
Hydrant and Access approval |
Cleared |
07/28/2015 |
JOHN DALLAS |
DAS Clearance |
Cleared |
07/31/2015 |
WAI LAU |
Sewer availability |
Cleared |
08/05/2015 |
ARMENIA HERNANDEZ |
Fire Marshall Fire Life Safety |
Cleared |
08/12/2015 |
DAVE MYERS |
Methane Ordinance |
Cleared |
08/12/2015 |
DAVE MYERS |
Green Code |
Cleared |
09/04/2015 |
RUSSELL KELLY |
"D" conditions |
Cleared |
09/09/2015 |
ALFREDO PEREZ |
"Q" conditions |
Cleared |
09/09/2015 |
ALFREDO PEREZ |
Bicycle Parking |
Cleared |
09/09/2015 |
ARMENIA HERNANDEZ |
Food Service Establishment |
Cleared |
09/09/2015 |
RAMESHBHAIR PATEL |
Miscellaneous |
Cleared |
09/09/2015 |
ALFREDO PEREZ |
Opn space landscape/Water mgmt |
Cleared |
09/09/2015 |
ALFREDO PEREZ |
Project located in CRA area |
Cleared |
09/09/2015 |
JIM URQUHART |
Site Plan review |
Cleared |
09/09/2015 |
ALFREDO PEREZ |
Tract Map conditions |
Cleared |
09/09/2015 |
ALFREDO PEREZ |
ZA Case |
Cleared |
09/09/2015 |
ALFREDO PEREZ |
Building over 3-story or 36-ft |
Cleared |
09/10/2015 |
CALOSHA APPROVED |
Excavation more than 5-ft deep |
Cleared |
09/10/2015 |
CALOSHA APPROVED |